14831 W ROSALES ST 91342
Certificate Information: 14831 W ROSALES ST 91342
- Application / Permit
- 23016-20000-39466
- Plan Check / Job No.
- B23VN15431
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20' X 22'1" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 4/12/2024
- Issuing Office
- Current Status
- CofO Issued on 10/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 11/14/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 3/28/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 4/3/2024 | MADISON O'DELL |
| No Progress | 4/9/2024 | MADISON O'DELL |
| Plan Check Approved | 4/9/2024 | MADISON O'DELL |
| Issued | 4/12/2024 | APPLICANT |
| CofO in Progress | 10/24/2024 | KEVIN BERBERYAN |
| Permit Finaled | 10/29/2024 | DANIEL ORRANTE |
| CofO Issued | 10/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/21/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 3/26/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Luisoni,, Antonio Stefano; Lic. No.: S1781 | 12757 DEON PLACE GRANADA HILLS, CA 91344 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/17/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 4/17/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/20/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 5/20/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 5/22/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 5/22/2024 | Partial Approval | KEVIN BERBERYAN |
| Insulation | 5/28/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/28/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/4/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 6/4/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/4/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 6/4/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/2/2024 | Approved | KEVIN BERBERYAN |
| Sewer | 7/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 9/27/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/27/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 9/27/2024 | Approved | KEVIN BERBERYAN |
| Final | 10/11/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 10/11/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | KEVIN BERBERYAN |