10123 N RINCON AVE 91331

Certificate Information: 10123 N RINCON AVE 91331

Application / Permit
23016-20000-39450
Plan Check / Job No.
B23VN15426
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETAHCED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). WORK DONE PER WFPP.
Permit Issued
Issued on 5/14/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 RAMA DABADGE
Corrections Issued 11/20/2023 RAMA DABADGE
Building Plans Picked Up 11/22/2023 APPLICANT
Issued 5/14/2024 APPLICANT
CofO in Progress 10/9/2024 MICHEL ABAJAN
Permit Finaled 10/23/2024 DANIEL ORRANTE
CofO Issued 10/23/2024 DANIEL ORRANTE
Permit Finaled 10/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/22/2023 BRYAN GODINEZ
Sewer availability Cleared 11/22/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/27/2023 BRYAN GODINEZ
Construction near power lines Cleared 5/1/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 5/21/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/5/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/5/2024 Approved MICHEL ABAJAN
Green Building Rough 6/5/2024 Approved MICHEL ABAJAN
METHANE-Rough 6/5/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 6/5/2024 Approved MICHEL ABAJAN
Insulation 6/17/2024 Approved WILLIAM WREN
Gas Test 6/18/2024 Approved MICHEL ABAJAN
HVAC-Final 6/18/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/18/2024 Approved MICHEL ABAJAN
Shower Pan 6/18/2024 Approved MICHEL ABAJAN
Drywall Nailing 7/1/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/24/2024 Approved MICHEL ABAJAN
Final 9/24/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 9/24/2024 Approved MICHEL ABAJAN
PLUMBING-Final 9/24/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 9/24/2024 Approved MICHEL ABAJAN
Final 9/27/2024 Corrections Issued MICHEL ABAJAN
Final 10/3/2024 OK to Issue CofO MICHEL ABAJAN