6908-6910 N ROYER AVE 91307
Certificate Information: 6908-6910 N ROYER AVE 91307
- Application / Permit
- 23016-20000-39391
- Plan Check / Job No.
- B23VN15379
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT A PORTION OF (E) ATTACHED GARAGE INTO A (N) IRREGULAR SHAPED JUNIOR ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) AND 65852.22 AND THE REST OF THE GARAGE INTO A (N) LAUNDRY AREA (ACCESS TO S.F.D. ONLY).
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Current Status
- CofO Issued on 10/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2023 | ALFRED RAMIREZ |
| Corrections Issued | 11/15/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 12/27/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 1/17/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/27/2024 | DANIEL SANJUAN |
| Issued | 4/5/2024 | APPLICANT |
| CofO in Progress | 10/2/2024 | GEVORK IPCHYAN |
| Permit Finaled | 10/23/2024 | JOHN JANSON |
| CofO Issued | 10/23/2024 | JOHN JANSON |
| Permit Finaled | 10/23/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/21/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 4/11/2024 | Conditional Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 4/30/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/30/2024 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 5/28/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 5/28/2024 | Partial Approval | GEVORK IPCHYAN |
| Special/Order Compliance | 5/28/2024 | Approved | HORACE FULTZ |
| Wood Frame | 5/28/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 5/31/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/31/2024 | Partial Approval | GEVORK IPCHYAN |
| PLUMBING-Rough | 5/31/2024 | Approved | GEVORK IPCHYAN |
| Wood Frame | 5/31/2024 | Partial Approval | GEVORK IPCHYAN |
| HVAC-Rough | 6/5/2024 | Approved | GEVORK IPCHYAN |
| Insulation | 6/5/2024 | Approved | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 6/5/2024 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Partial Approval | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 6/11/2024 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 6/11/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 6/14/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | GEVORK IPCHYAN |
| Final | 9/11/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 9/11/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 9/11/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 9/11/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 10/1/2024 | Approved | GEVORK IPCHYAN |
| Final | 10/1/2024 | OK to Issue CofO | GEVORK IPCHYAN |
| Green Building Final | 10/1/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 10/1/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 10/1/2024 | Approved | GEVORK IPCHYAN |