10900-10902 N RUFFNER AVE 91344
Certificate Information: 10900-10902 N RUFFNER AVE 91344
- Application / Permit
- 23016-20000-39319
- Plan Check / Job No.
- B23VN15355
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- CONVERT IRR. 19'-4" X 34'-3" PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.229. REMODEL SFD AND ADD A NEW BTHRM.
- Permit Issued
- Issued on 12/28/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2023 | JESSE ARELLANO |
| Corrections Issued | 11/14/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 11/16/2023 | APPLICANT |
| Applicant returned to address corrections | 12/21/2023 | JESSE ARELLANO |
| Issued | 12/28/2023 | APPLICANT |
| CofO in Progress | 3/6/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
| CofO Issued | 3/26/2026 | RUBEN SALAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 11/15/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 2/1/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/3/2024 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/3/2024 | No Access for Inspection | MATTHEW NELSON |
| HVAC-Rough | 4/3/2024 | No Access for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 4/3/2024 | No Access for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/10/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/10/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/10/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/10/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 4/12/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/16/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/16/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 4/16/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/19/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 4/19/2024 | Approved | MISAEL ESPARZA |
| Final | 10/7/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/7/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Final | 11/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 2/17/2026 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 2/17/2026 | Not Ready for Inspection | KIRK SANDERS |
| Final | 2/20/2026 | No Access for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Not Required | CHRISTOPHER ROJAS |
| Smoke Detectors | 2/20/2026 | No Access for Inspection | CHRISTOPHER ROJAS |
| Final | 2/26/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 2/26/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 3/5/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/5/2026 | Approved | CHRISTOPHER ROJAS |