8666-8668 N SHARP AVE 91352
Certificate Information: 8666-8668 N SHARP AVE 91352
- Application / Permit
- 23016-20000-39069
- Plan Check / Job No.
- B23VN15274
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Conversion of attached garage to ADU per CA Govt. Code 65852.2(e)(1)(A). All work done per engineered design.
- Permit Issued
- Issued on 4/24/2024
- Issuing Office
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2023 | DANIEL SMILEY |
| Corrections Issued | 11/16/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 4/4/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 4/10/2024 | NEHEMIAS RAMOS |
| Issued | 4/24/2024 | APPLICANT |
| CofO in Progress | 8/6/2025 | MATTHEW NELSON |
| Permit Finaled | 8/26/2025 | RUBEN SALAS |
| Permit Finaled | 8/26/2025 | RUBEN SALAS |
| CofO Issued | 8/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2023 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 12/4/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 12/4/2023 | BRYAN GODINEZ |
| "T" removal | Cleared | 1/25/2024 | DALIA MOKAYED |
Contact Information
| Contractor | J B Builders Fire Protection Inc; Lic. No.: 923970-B | , |
| Contractor | J B New Construction Inc; Lic. No.: 923970-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/28/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 5/28/2024 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 5/28/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/6/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/6/2024 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/10/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/10/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 9/10/2024 | Approved | MATTHEW NELSON |
| METHANE-Rough | 9/10/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 9/10/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/13/2024 | Approved | MATTHEW NELSON |
| Insulation | 9/13/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/17/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/17/2024 | Approved | MATTHEW NELSON |
| Final | 4/7/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/7/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 4/7/2025 | Approved | MATTHEW NELSON |
| Final | 7/28/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | MATTHEW NELSON |
| Final | 8/5/2025 | OK to Issue CofO | MATTHEW NELSON |