19101-19103 W CHASE ST 91324

Certificate Information: 19101-19103 W CHASE ST 91324

Application / Permit
23016-20000-38197
Plan Check / Job No.
B23VN14928
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT REC RM TO (N) 406 SF JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 12/11/2023
Issuing Office
Current Status
CofO Issued on 12/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/3/2023 SERGIO MUNIZ
Corrections Issued 11/4/2023 SERGIO MUNIZ
Building Plans Picked Up 11/13/2023 APPLICANT
Issued 12/11/2023 APPLICANT
CofO in Progress 12/10/2025 DAVID SCANTLIN
Permit Finaled 12/13/2025 MICHAEL PELHAM
Permit Finaled 12/13/2025 MICHAEL PELHAM
CofO Issued 12/13/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 11/9/2023 CARLOS RAMIREZ
Sewer availability Cleared 11/9/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/11/2023 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/19/2023 No Access for Inspection DAVID SCANTLIN
Final 12/19/2023 No Access for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 12/19/2023 No Access for Inspection DAVID SCANTLIN
Pre-Inspection 10/3/2024 Partial Inspection KRISTEN CAUSEY
PLUMBING-Rough 5/7/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 7/18/2025 Approved DAVID SCANTLIN
Deputy Wood Construction 7/23/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 7/29/2025 Approved KRISTEN CAUSEY
Drywall Nailing 9/9/2025 Approved DAVID SCANTLIN
Insulation 9/9/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/9/2025 Approved DAVID SCANTLIN
ELECTRICAL-Final 12/5/2025 Approved DAVID SCANTLIN
Final 12/5/2025 Corrections Issued DAVID SCANTLIN
PLUMBING-Final 12/5/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 12/5/2025 Approved DAVID SCANTLIN
Final 12/10/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 12/10/2025 Approved DAVID SCANTLIN
HVAC-Final 12/10/2025 Approved DAVID SCANTLIN
Service/Power Release 12/10/2025 Approved DAVID SCANTLIN