10564 N PEACH AVE 91345

Certificate Information: 10564 N PEACH AVE 91345

Application / Permit
23016-20000-38010
Plan Check / Job No.
B23VN14888
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: convert existing detached garage into ADU per WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/13/2023
Issuing Office
Current Status
CofO Issued on 7/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2023 APPLICANT
Assigned to Plan Check Engineer 10/31/2023 AUNG SOE
Corrections Issued 11/2/2023 AUNG SOE
Plan Check Approved 11/10/2023 KHUONG TRUONG
Issued 11/13/2023 APPLICANT
CofO in Progress 6/25/2024 JENNIFER RABUCHIN
CofO Issued 7/8/2024 RUBEN SALAS
Permit Finaled 7/8/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/4/2023 COLIN LOREDO
Sewer availability Cleared 11/4/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/6/2023 COLIN LOREDO

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/27/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 12/27/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/10/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 1/10/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/10/2024 Approved JENNIFER RABUCHIN
Sewer 1/10/2024 Approved JENNIFER RABUCHIN
Wood Frame 1/10/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/11/2024 Approved JENNIFER RABUCHIN
Gas Test 1/11/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 1/11/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/18/2024 Approved DANIEL ORRANTE
Insulation 1/23/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/23/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 1/23/2024 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 1/25/2024 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 1/29/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/20/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/20/2024 Approved JENNIFER RABUCHIN
Final 6/20/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 6/20/2024 Approved JENNIFER RABUCHIN
Green Building Rough 6/20/2024 Approved JENNIFER RABUCHIN
HVAC-Final 6/20/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/20/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 6/20/2024 Conditional Approval JENNIFER RABUCHIN
Smoke Detectors 6/20/2024 Approved JENNIFER RABUCHIN
Final 6/25/2024 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 6/25/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 6/25/2024 Approved JENNIFER RABUCHIN