14232 W ERWIN ST 1-10 91401
Certificate Information: 14232 W ERWIN ST 1-10 91401
- Application / Permit
- 23016-20000-37902
- Plan Check / Job No.
- B23VN14861
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan: Conversion of an attached Carport on south side into an (894.98 SF) Accessory Dwelling Unit with a (17.22 SF) Laundry Room and conversion of attached Carport on north side into an (201.25 SF) Accessory Dwelling Unit for a total of 2 Accessory Dwelling Units per CA Govt. Code 65852.2(e)(1)(C)
- Permit Issued
- Issued on 3/1/2024
- Issuing Office
- Current Status
- Issued on 3/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 11/12/2023 | VAHAN JIVALAGIAN |
| Assigned to Zoning Architect | 11/17/2023 | SARHAD GHEVANDIAN |
| Quality Review Completed | 11/21/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 12/14/2023 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 12/27/2023 | VAHAN JIVALAGIAN |
| Plan Check Approved | 1/5/2024 | VAHAN JIVALAGIAN |
| Issued | 3/1/2024 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/14/2023 | STEVEN WECHSLER |
| Tenant Habitability Plan | Cleared | 11/15/2023 | RICARDO BOHORQUEZ |
| DAS Clearance | Cleared | 11/16/2023 | Ricardo Ramirez Solis |
| Address approval | Cleared | 11/17/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 11/17/2023 | NIKKI ZULUETA |
| CPC | Cleared | 12/12/2023 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2023 | NIKKI ZULUETA |
| Zoning Plan Check | Cleared | 12/20/2023 | Ricardo Ramirez Solis |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | , |
| Engineer | Pajuhesh,, Jamshid; Lic. No.: S1860 | 6824 LOUISE AVE VAN NUYS, CA 91406 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/22/2024 | Approved | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 10/7/2024 | Conditional Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 10/8/2024 | Approved | STEVEN LEVITT |
| Deputy Reinf. Concrete | 10/10/2024 | Conditional Approval | STEVEN LEVITT |
| Green Building Rough | 3/3/2025 | Approved | ROBERT DAVIS |
| Wood Frame | 3/3/2025 | Corrections Issued | ROBERT DAVIS |
| Wood Frame | 3/17/2025 | Partial Approval | ROBERT DAVIS |
| Insulation | 3/26/2025 | Partial Inspection | BRIAN KELLY |
| Insulation | 4/4/2025 | Not Ready for Inspection | ROBERT DAVIS |
| Drywall Nailing | 4/10/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 4/10/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Final | 4/10/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 4/10/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 4/10/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 4/21/2025 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 4/25/2025 | Approved | ROBERT DAVIS |
| Insulation | 5/1/2025 | Approved | ANDREW DORSO |
| Drywall Nailing | 5/9/2025 | Approved | ANDREW DORSO |