13968 W WEIDNER ST 91331

Certificate Information: 13968 W WEIDNER ST 91331

Application / Permit
23016-20000-37698
Plan Check / Job No.
B23VN14312
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing Rec room and storage to new single family dwelling per SB9, NFPA 13D sprinkler is required thru-out. All work done per engineer.
Permit Issued
Issued on 12/27/2023
Issuing Office
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 NAREG ATARIAN
Corrections Issued 10/26/2023 NAREG ATARIAN
Quality Review Completed 11/1/2023 OMID HEDAYAT
Applicant returned to address corrections 12/21/2023 NAREG ATARIAN
Plan Check Approved 12/22/2023 NAREG ATARIAN
Issued 12/27/2023 APPLICANT
CofO in Progress 7/1/2024 MICHEL ABAJAN
Permit Finaled 7/10/2024 RUBEN SALAS
CofO Issued 7/10/2024 RUBEN SALAS
Permit Finaled 7/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/9/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/9/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/13/2023 LEE GUILBEAUX
Sewer availability Cleared 11/13/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/18/2023 LEE GUILBEAUX
Senate Bill 9 Cleared 11/20/2023 ASHLEY RODARTE
Hydrant and Access approval Cleared 12/2/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: C69935 16873 MCKEEVER ST      GRANADA HILLS, CA 91344
Engineer Yeghiayan,, Armond; Lic. No.: NA69935       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/1/2024 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/13/2024 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 3/13/2024 Approved MATTHEW NELSON
PLUMBING-Rough 3/13/2024 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 3/22/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 3/22/2024 Approved MICHEL ABAJAN
Green Building Rough 3/22/2024 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 3/22/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 3/22/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/26/2024 Approved MICHEL ABAJAN
Green Building Rough 4/26/2024 Approved MICHEL ABAJAN
HVAC-Rough 4/26/2024 Approved MICHEL ABAJAN
Insulation 5/6/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 5/6/2024 Partial Approval JACK KARGODORIAN
Drywall Nailing 5/20/2024 Approved KEVIN BERBERYAN
Final 6/17/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/17/2024 Approved JENNIFER RABUCHIN
MERV13>=Final 6/17/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 6/17/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/26/2024 Approved MICHEL ABAJAN
Final 6/26/2024 Corrections Issued MICHEL ABAJAN
Gas Test 6/26/2024 Approved MICHEL ABAJAN
HVAC-Final 6/26/2024 Approved MICHEL ABAJAN
PLUMBING-Final 6/26/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 6/26/2024 Not Ready for Inspection MICHEL ABAJAN
Final 7/1/2024 OK to Issue CofO MICHEL ABAJAN