9922 N TELFAIR AVE 91331

Certificate Information: 9922 N TELFAIR AVE 91331

Application / Permit
23016-20000-37679
Plan Check / Job No.
B23VN14793
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT (360SQFT) PER STATE LAW - WORK DONE PER WFPP
Permit Issued
Issued on 12/23/2023
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/1/2023 KHUONG TRUONG
Corrections Issued 11/2/2023 KHUONG TRUONG
Applicant returned to address corrections 12/8/2023 KHUONG TRUONG
Plan Check Approved 12/20/2023 DANIEL ABRAMYAN
Issued 12/23/2023 APPLICANT
CofO in Progress 10/11/2024 MICHEL ABAJAN
Permit Finaled 10/25/2024 DANIEL ORRANTE
CofO Issued 10/25/2024 DANIEL ORRANTE
Permit Finaled 10/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/19/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/19/2023 COLIN LOREDO
Sewer availability Cleared 12/19/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/30/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/10/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 6/10/2024 Partial Approval MICHEL ABAJAN
Underground Mechanical 7/31/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/7/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/7/2024 Approved MICHEL ABAJAN
Green Building Rough 8/7/2024 Approved MICHEL ABAJAN
Insulation 8/7/2024 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 8/7/2024 Approved MICHEL ABAJAN
Insulation 8/9/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/9/2024 Approved MICHEL ABAJAN
Drywall Nailing 8/14/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/16/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/8/2024 Approved MICHEL ABAJAN
Final 10/8/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 10/8/2024 Approved MICHEL ABAJAN
HVAC-Final 10/8/2024 Approved MICHEL ABAJAN
PLUMBING-Final 10/8/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 10/8/2024 Approved MICHEL ABAJAN
Final 10/10/2024 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Approved MICHEL ABAJAN