19801-19803 W GRESHAM ST 91324

Certificate Information: 19801-19803 W GRESHAM ST 91324

Application / Permit
23016-20000-37592
Plan Check / Job No.
B23VN14740
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 1/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2023 APPLICANT
Assigned to Plan Check Engineer 10/27/2023 JEROME MAGAT PALMA
Corrections Issued 10/28/2023 JEROME MAGAT PALMA
Building Plans Picked Up 10/31/2023 APPLICANT
Plan Check Approved 1/2/2024 ISIS ARGUETA
Issued 1/2/2024 APPLICANT
CofO in Progress 10/23/2024 JEFFREY HARTLINE
Permit Finaled 11/4/2024 JOHN JANSON
CofO Issued 11/4/2024 JOHN JANSON
Permit Finaled 11/4/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/1/2023 BRYAN GODINEZ
Sewer availability Cleared 11/1/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/20/2023 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/21/2024 Partial Approval HENRY KIM
Footing/Foundation/Slab 3/22/2024 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 4/24/2024 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/10/2024 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/10/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 5/10/2024 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/10/2024 Approved CHRIS CHRISTENSEN
Special/Order Compliance 5/10/2024 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 5/10/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/7/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 6/7/2024 Corrections Issued JEFFREY HARTLINE
Green Building Rough 6/7/2024 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 6/7/2024 Corrections Issued JEFFREY HARTLINE
Wood Frame 6/7/2024 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 6/20/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 6/20/2024 Approved JEFFREY HARTLINE
Green Building Rough 6/20/2024 Approved JEFFREY HARTLINE
HVAC-Rough 6/20/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 6/20/2024 Approved JEFFREY HARTLINE
Wood Frame 6/20/2024 Approved JEFFREY HARTLINE
Insulation 6/28/2024 Approved JEFFREY HARTLINE
Drywall Nailing 7/15/2024 Approved JEFFREY HARTLINE
Final 10/4/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 10/4/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 10/4/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 10/4/2024 Approved JEFFREY HARTLINE
Final 10/22/2024 OK to Issue CofO JEFFREY HARTLINE