- ENCLOSE IRREGULAR SHAPED (179 SF ) PORTION OF (E) PATIO COVER TO CONVERT INTO A (N) BEDROOM AND BATHROOM AND CONVERT (E) (110 SF) BEDROOM INTO A DEN/LIVING ROOM FOR (E) S.F.D. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Valley
- Current Status
- Issued on 2/9/2024
Permit Application Status History
| Submitted | 10/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2023 | JESSE ARELLANO |
| Corrections Issued | 10/31/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 11/17/2023 | APPLICANT |
| Applicant returned to address corrections | 1/22/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/31/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 2/6/2024 | MIROOSH KHACHATOORIAN |
| Issued | 2/9/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/24/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 2/7/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salgado,, Erica; Lic. No.: C93745 | 7912 LATHAM CT. APT A BAKERSFIELD, CA 93307 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/29/2024 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/4/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 5/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/7/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/7/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/21/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/21/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/21/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 5/21/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/3/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 6/3/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 6/11/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/11/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/17/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| Final | 7/5/2024 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/5/2024 | Approved | JENNIFER RABUCHIN |