7337 N LOUISE AVE 91406

Certificate Information: 7337 N LOUISE AVE 91406

Application / Permit
23016-20000-37377
Plan Check / Job No.
B23VN14657
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 11/28/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2023 APPLICANT
Assigned to Plan Check Engineer 10/28/2023 ARTIN ZARUKIAN
Corrections Issued 10/28/2023 ARTIN ZARUKIAN
Building Plans Picked Up 11/1/2023 APPLICANT
Plan Check Approved 11/28/2023 SERGIO MUNIZ
Issued 11/28/2023 APPLICANT
CofO in Progress 7/17/2025 SALVADOR MARTINEZ
Permit Finaled 7/29/2025 RUBEN SALAS
CofO Issued 7/29/2025 RUBEN SALAS
Permit Finaled 7/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/3/2023 EDGAR ALCARAZ
Sewer availability Cleared 11/3/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/21/2023 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/22/2024 Approved RAUL OLAGI
Deputy Drilled-In Anchors 7/9/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/11/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/11/2024 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 7/12/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/12/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 7/12/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 7/16/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 7/19/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/17/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 3/17/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 3/17/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 3/17/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 4/7/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 4/9/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 4/9/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 4/9/2025 Approved GAREN HAYRAPETYAN
Insulation 4/11/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/11/2025 Partial Approval GAREN HAYRAPETYAN
Shower Pan 4/11/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 4/16/2025 Partial Approval NICHOLAS TROWBRIDGE
Green Building Rough 4/16/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 4/16/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/1/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 7/1/2025 Approved SALVADOR MARTINEZ
Final 7/1/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 7/1/2025 Approved SALVADOR MARTINEZ
Green Building Rough 7/1/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 7/1/2025 Approved SALVADOR MARTINEZ
Final 7/7/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 7/11/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Ready SALVADOR MARTINEZ
Final 7/16/2025 OK to Issue CofO SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 7/16/2025 Approved SALVADOR MARTINEZ