10474 W WILKINS AVE 90024

Certificate Information: 10474 W WILKINS AVE 90024

Application / Permit
23016-20000-37197
Plan Check / Job No.
B23VN14579
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and Major Remodel to existing 1-story Single Family Dwelling, only 6 linear feet of exterior wall and foundation to remain. Rebuilt as 2-story (61' x 36' Irregular Shape) Single Family Dwelling, attached garage. NFPA 13D Fire Sprinklers Throughout. All work done per engineer.
Permit Issued
Issued on 7/18/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2023 APPLICANT
Assigned to Plan Check Engineer 11/2/2023 NAREG ATARIAN
Corrections Issued 11/3/2023 NAREG ATARIAN
Quality Review Completed 11/8/2023 OMID HEDAYAT
Building Plans Picked Up 11/13/2023 APPLICANT
Applicant returned to address corrections 2/28/2024 NAREG ATARIAN
Plan Check Approved 7/18/2024 CHRIS JOHNSON
Issued 7/18/2024 APPLICANT
CofO in Progress 1/6/2026 DANIEL VERA
Permit Finaled 1/13/2026 RICHARD STEINBACH
CofO Issued 1/13/2026 RICHARD STEINBACH
Permit Finaled 1/13/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/7/2023 LIAM ODONOVAN
Sewer availability Cleared 12/7/2023 LIAM ODONOVAN
Specific Plan Cleared 12/18/2023 EDUARDO HERMOSO
Metro Rail approval Cleared 12/27/2023 JENNIFER SU
Low Impact Development (LID) Cleared 1/4/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 1/5/2024 LIAM ODONOVAN
Trees in Parkway Cleared 3/28/2024 ADALBERTO VERA
Permit Cleared 4/8/2024 ANTHONY MAINEZ
GPI Written Notices Cleared 4/22/2024 MATTHEW JENKINS
Grading Pre-Inspection Cleared 4/22/2024 MATTHEW JENKINS

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 20600 VENTURA BLVD UNIT 2319      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/18/2024 Partial Approval ARAM AVEDISIAN
METHANE-Rough 10/30/2024 Not Ready for Inspection STEPHANIE SWANSON
METHANE-Subgrade 10/30/2024 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/5/2024 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 12/5/2024 Not Ready for Inspection STEPHANIE SWANSON
METHANE-Barrier 12/5/2024 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/10/2024 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 12/10/2024 Approved STEPHANIE SWANSON
Deputy Drilled-In Anchors 1/15/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 2/27/2025 Conditional Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Partial Approval DANIEL VERA
PLUMBING-Rough 4/17/2025 Approved DANIEL VERA
Sewer 4/17/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 4/29/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 4/29/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 4/29/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 5/5/2025 Approved DANIEL VERA
HVAC-Rough 5/5/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 5/27/2025 Corrections Issued DANIEL VERA
Green Building Rough 5/27/2025 Approved DANIEL VERA
Interior/Exterior Lathing 5/27/2025 Partial Approval DANIEL VERA
METHANE-Rough 5/27/2025 Not Ready for Inspection DANIEL VERA
Shower Pan 5/27/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 5/29/2025 Approved MEL KHACHATOURIAN
METHANE-Rough 5/29/2025 Approved MEL KHACHATOURIAN
Insulation 6/2/2025 Corrections Issued JAYLIN GRAVITTE
Insulation 6/5/2025 Approved SEAN HAUPT
Drywall Nailing 6/10/2025 Approved DANIEL VERA
Interior/Exterior Lathing 6/10/2025 Approved DANIEL VERA
ELECTRICAL-Final 12/17/2025 Approved EVAN COOPER
HVAC-Final 12/17/2025 Approved EVAN COOPER
Gas Test 12/22/2025 Approved KIRK SANDERS
PLUMBING-Final 12/22/2025 Approved KIRK SANDERS
Green Building Final 12/23/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Approved EVAN COOPER
Service/Power Release 12/23/2025 Not Ready for Inspection EVAN COOPER
Smoke Detectors 12/23/2025 Approved EVAN COOPER
Pre-Inspection 12/30/2025 Approved DANIEL VERA
Service/Power Release 12/30/2025 Approved DANIEL VERA
ELECTRICAL-Final 1/2/2026 Corrections Issued CARLOS MATAMOROS
Final 1/2/2026 Partial Approval CARLOS MATAMOROS
Service/Power Release 1/2/2026 Approved CARLOS MATAMOROS
Final 1/5/2026 OK to Issue CofO DANIEL VERA