10474 W WILKINS AVE 90024
Certificate Information: 10474 W WILKINS AVE 90024
- Application / Permit
- 23016-20000-37197
- Plan Check / Job No.
- B23VN14579
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Major Remodel to existing 1-story Single Family Dwelling, only 6 linear feet of exterior wall and foundation to remain. Rebuilt as 2-story (61' x 36' Irregular Shape) Single Family Dwelling, attached garage. NFPA 13D Fire Sprinklers Throughout. All work done per engineer.
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2023 | NAREG ATARIAN |
| Corrections Issued | 11/3/2023 | NAREG ATARIAN |
| Quality Review Completed | 11/8/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 11/13/2023 | APPLICANT |
| Applicant returned to address corrections | 2/28/2024 | NAREG ATARIAN |
| Plan Check Approved | 7/18/2024 | CHRIS JOHNSON |
| Issued | 7/18/2024 | APPLICANT |
| CofO in Progress | 1/6/2026 | DANIEL VERA |
| Permit Finaled | 1/13/2026 | RICHARD STEINBACH |
| CofO Issued | 1/13/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/13/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2023 | LIAM ODONOVAN |
| Sewer availability | Cleared | 12/7/2023 | LIAM ODONOVAN |
| Specific Plan | Cleared | 12/18/2023 | EDUARDO HERMOSO |
| Metro Rail approval | Cleared | 12/27/2023 | JENNIFER SU |
| Low Impact Development (LID) | Cleared | 1/4/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 1/5/2024 | LIAM ODONOVAN |
| Trees in Parkway | Cleared | 3/28/2024 | ADALBERTO VERA |
| Permit | Cleared | 4/8/2024 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 4/22/2024 | MATTHEW JENKINS |
| Grading Pre-Inspection | Cleared | 4/22/2024 | MATTHEW JENKINS |
Contact Information
| Architect | Janev,, Valentine S; Lic. No.: C19379 | 20600 VENTURA BLVD UNIT 2319 WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/18/2024 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Rough | 10/30/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 10/30/2024 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/5/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/5/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Barrier | 12/5/2024 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/10/2024 | Approved | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 1/15/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 2/27/2025 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 4/17/2025 | Approved | DANIEL VERA |
| Sewer | 4/17/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 4/29/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/29/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 4/29/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 5/5/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 5/5/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 5/27/2025 | Corrections Issued | DANIEL VERA |
| Green Building Rough | 5/27/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 5/27/2025 | Partial Approval | DANIEL VERA |
| METHANE-Rough | 5/27/2025 | Not Ready for Inspection | DANIEL VERA |
| Shower Pan | 5/27/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 5/29/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/2/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Insulation | 6/5/2025 | Approved | SEAN HAUPT |
| Drywall Nailing | 6/10/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 6/10/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 12/17/2025 | Approved | EVAN COOPER |
| HVAC-Final | 12/17/2025 | Approved | EVAN COOPER |
| Gas Test | 12/22/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 12/22/2025 | Approved | KIRK SANDERS |
| Green Building Final | 12/23/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 12/23/2025 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 12/23/2025 | Approved | EVAN COOPER |
| Pre-Inspection | 12/30/2025 | Approved | DANIEL VERA |
| Service/Power Release | 12/30/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 1/2/2026 | Corrections Issued | CARLOS MATAMOROS |
| Final | 1/2/2026 | Partial Approval | CARLOS MATAMOROS |
| Service/Power Release | 1/2/2026 | Approved | CARLOS MATAMOROS |
| Final | 1/5/2026 | OK to Issue CofO | DANIEL VERA |