10100-10102 N SOPHIA AVE 91343

Certificate Information: 10100-10102 N SOPHIA AVE 91343

Application / Permit
23016-20000-37048
Plan Check / Job No.
B23VN14514
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Attached Garage Conversion to a 400 sf A.D.U. per CA Govt. Code 65852.2(e)(1)(A). All Work per WFPP
Permit Issued
Issued on 11/29/2023
Issuing Office
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2023 APPLICANT
Assigned to Plan Check Engineer 10/25/2023 EDWIN ESPIN
Corrections Issued 10/26/2023 EDWIN ESPIN
Applicant returned to address corrections 11/17/2023 ALFREDO JARA
Plan Check Approved 11/28/2023 ALFREDO JARA
Issued 11/29/2023 APPLICANT
CofO in Progress 7/22/2024 JAVIER RAMOS JR
Permit Finaled 9/10/2024 DANIEL ORRANTE
CofO Issued 9/10/2024 DANIEL ORRANTE
Permit Finaled 9/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/31/2023 CARLOS RAMIREZ
Sewer availability Cleared 10/31/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/1/2023 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 11/1/2023 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2024 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/9/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 4/10/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 4/10/2024 Partial Approval JAVIER RAMOS JR
Sewer 4/10/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 4/12/2024 Not Ready for Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 4/12/2024 Not Ready for Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 4/15/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/31/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 5/31/2024 Approved JAVIER RAMOS JR
HVAC-Rough 5/31/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 5/31/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/5/2024 Approved JAVIER RAMOS JR
Insulation 6/5/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 6/5/2024 Partial Approval JAVIER RAMOS JR
Shower Pan 6/5/2024 Approved JAVIER RAMOS JR
Drywall Nailing 6/10/2024 Approved JAVIER RAMOS JR
Insulation 6/10/2024 Approved JAVIER RAMOS JR
Final 7/15/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 7/15/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 7/15/2024 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Final 7/19/2024 Approved JAVIER RAMOS JR
Final 7/19/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 7/19/2024 Approved JAVIER RAMOS JR
HVAC-Final 7/19/2024 Approved JAVIER RAMOS JR
Service/Power Release 7/19/2024 Approved JAVIER RAMOS JR
Smoke Detectors 7/19/2024 Approved JAVIER RAMOS JR