8656 N LEHIGH AVE 91352
Certificate Information: 8656 N LEHIGH AVE 91352
- Application / Permit
- 23016-20000-36927
- Plan Check / Job No.
- B23VN14467
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Conversion of (E) detached garage into detached (N) 480 SF ADU per GCS 65852.2(e)(1)(A), ALL work per WFPP
- Permit Issued
- Issued on 11/16/2023
- Issuing Office
- Current Status
- CofO Issued on 8/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2023 | RAMA DABADGE |
| Corrections Issued | 10/25/2023 | RAMA DABADGE |
| Building Plans Picked Up | 10/26/2023 | APPLICANT |
| Issued | 11/16/2023 | APPLICANT |
| CofO in Progress | 7/19/2024 | DAVID ANDERSON |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
| CofO Issued | 8/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 10/30/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | GABRIELLA TORRES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/28/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/28/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/7/2024 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 2/7/2024 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 2/7/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/12/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/12/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/12/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 2/12/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/12/2024 | Approved | DAVID ANDERSON |
| Insulation | 2/14/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 2/14/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 2/21/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/21/2024 | Approved | DAVID ANDERSON |
| Final | 7/18/2024 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 7/18/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 7/18/2024 | Approved | DAVID ANDERSON |