998 1/4 E 54TH ST 90011

Certificate Information: 998 1/4 E 54TH ST 90011

Application / Permit
23016-20000-36564
Plan Check / Job No.
B23VN14319
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO NEW 390 SF DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/18/2024
Issuing Office
Current Status
Issued on 3/18/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/25/2023 APPLICANT
Assigned to Plan Check Engineer 10/27/2023 MIROOSH KHACHATOORIAN
Corrections Issued 10/28/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 3/6/2024 LUISANGEL VALENZUELA
Issued 3/18/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/9/2024 WALLIE JONG
Sewer availability Cleared 1/9/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/28/2024 WALLIE JONG

Contact Information

Contractor G Tech Smart Inc; Lic. No.: 1047801-B       ,
Contractor G Tech Smart Remodeling; Lic. No.: 1047801-B       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/23/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 5/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 5/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/31/2024 Corrections Issued ANTHONY EGSON
Sewer 5/31/2024 Approved ANTHONY EGSON
Underground Mechanical 5/31/2024 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 6/5/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/5/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/24/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 6/24/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 6/24/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 6/24/2024 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 6/28/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 6/28/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/28/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Partial Approval MICHAEL LEWIS
Insulation 7/3/2024 Partial Approval MICHAEL LEWIS
Interior/Exterior Lathing 7/3/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 7/3/2024 Approved MICHAEL LEWIS
Shower Pan 7/3/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 7/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 7/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/17/2024 Approved ALEJANDRO DE ARTOLA
Insulation 7/17/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/23/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Not Ready JOHN QUINTANILLA
ELECTRICAL-Final 11/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/14/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 11/14/2024 Approved ALEJANDRO DE ARTOLA