7866 N CANTALOUPE AVE 91402
Certificate Information: 7866 N CANTALOUPE AVE 91402
- Application / Permit
- 23016-20000-36476
- Plan Check / Job No.
- B23VN14288
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). (E) ATTACHED CARPORT TO REMAIN. WORK TO BE DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/13/2024
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | MADISON ODELL |
| Corrections Issued | 10/20/2023 | MADISON ODELL |
| Applicant returned to address corrections | 2/22/2024 | MADISON ODELL |
| Plan Check Approved | 3/6/2024 | ALEC MOUSAKHANIAN |
| Issued | 3/13/2024 | APPLICANT |
| CofO in Progress | 11/22/2024 | GREGG CUMMINGS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/1/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2023 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 2/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/14/2024 | Approved | VINCENT HANLEY |
| Sewer | 5/14/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 5/14/2024 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 5/22/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/22/2024 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/28/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/10/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 7/10/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 7/10/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/16/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 7/16/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 7/16/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/7/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 8/7/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Shower Pan | 8/7/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/15/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 8/15/2024 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/15/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/29/2024 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/29/2024 | Approved | DAVID ANDERSON |
| Insulation | 8/29/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/4/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/9/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/9/2024 | Partial Approval | GREGG CUMMINGS |
| Final | 11/12/2024 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 11/12/2024 | Approved | GREGG CUMMINGS |
| Green Building Final | 11/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 11/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 11/12/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/15/2024 | Approved | GREGG CUMMINGS |
| Final | 11/15/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/15/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 11/15/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 11/15/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 11/15/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/21/2024 | Approved | GREGG CUMMINGS |
| Final | 11/21/2024 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 11/21/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 11/21/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 11/21/2024 | Approved | GREGG CUMMINGS |