20760 W SKOURAS DR 91306
Certificate Information: 20760 W SKOURAS DR 91306
- Application / Permit
- 23016-20000-36282
- Plan Check / Job No.
- B23VN14221
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Conversion of existing detached recreation room with storage at rear of lot to accessory dwelling unit per state law. All work done per WFPP. (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 2/16/2024
- Issuing Office
- Current Status
- CofO Issued on 8/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2023 | DANIEL SMILEY |
| Corrections Issued | 10/23/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 11/1/2023 | AUNG SOE |
| Plan Check Approved | 2/1/2024 | AUNG SOE |
| Issued | 2/16/2024 | APPLICANT |
| CofO in Progress | 7/24/2024 | ARUTYUN MADATYAN |
| Permit Finaled | 8/12/2024 | JOHN JANSON |
| Permit Finaled | 8/12/2024 | JOHN JANSON |
| CofO Issued | 8/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 10/27/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 1/29/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/29/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/14/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/14/2024 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 3/14/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 4/9/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 4/9/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/9/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 4/24/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/24/2024 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 4/24/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 5/22/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/19/2024 | Approved | ALEXANDER HANDY |
| Final | 7/19/2024 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 7/19/2024 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 7/19/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 7/23/2024 | Approved | ARUTYUN MADATYAN |
| Final | 7/23/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 7/23/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 7/23/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 7/23/2024 | SGSOV Approved | ARUTYUN MADATYAN |