3899-3899 1/2 S 2ND AVE 90008

Certificate Information: 3899-3899 1/2 S 2ND AVE 90008

Application / Permit
23016-20000-35921
Plan Check / Job No.
B23VN14113
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO NEW ATTACHED JADU PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK DONE PER WFPP.
Permit Issued
Issued on 12/15/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 MIROOSH KHACHATOORIAN
Building Plans Picked Up 10/26/2023 APPLICANT
Corrections Issued 11/28/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 12/5/2023 KAMYAR EMAMI
Applicant returned to address corrections 12/8/2023 DANIEL ABRAMYAN
Plan Check Approved 12/12/2023 RAMA DABADGE
Issued 12/15/2023 APPLICANT
CofO in Progress 2/20/2024 BRENDAN MORELLI
CofO Issued 2/22/2024 DEROLD HAUFF
Permit Finaled 2/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 11/4/2023 TERRY PHAN
Address approval Cleared 11/6/2023 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 11/6/2023 TERRY PHAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/20/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 1/2/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 1/2/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 1/2/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 1/3/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 1/3/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 1/3/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 1/17/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Approved ANTHONY EGSON
Green Building Rough 1/17/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 1/17/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 1/22/2024 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 1/22/2024 Not Ready for Inspection ANTHONY EGSON
Insulation 1/25/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/25/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/29/2024 Approved ANTHONY EGSON
Drywall Nailing 1/29/2024 Approved ANTHONY EGSON
Green Building Rough 1/29/2024 Approved ANTHONY EGSON
Final 2/12/2024 Corrections Issued BRENDAN MORELLI
Green Building Final 2/12/2024 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 2/12/2024 Approved BRENDAN MORELLI
Final 2/16/2024 OK to Issue CofO BRENDAN MORELLI
Green Building Final 2/16/2024 Approved BRENDAN MORELLI