10654-10656 N TAMARACK AVE 91331

Certificate Information: 10654-10656 N TAMARACK AVE 91331

Application / Permit
23016-20000-35742
Plan Check / Job No.
B23VN14057
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) ATTACHED GARAGE TO (N) 440 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) TO (E) DUPLEX.
Permit Issued
Issued on 11/16/2023
Issuing Office
Valley
Current Status
Issued on 11/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/12/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 JEROME MAGAT PALMA
Corrections Issued 10/19/2023 JEROME MAGAT PALMA
Building Plans Picked Up 10/31/2023 APPLICANT
Issued 11/16/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/31/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/31/2023 LEE GUILBEAUX
Sewer availability Cleared 10/31/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/12/2024 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 1/12/2024 Approved MICHEL ABAJAN
HVAC-Rough 1/12/2024 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 1/12/2024 Partial Inspection MICHEL ABAJAN
Wood Frame 1/17/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/19/2024 Approved MICHEL ABAJAN
HVAC-Rough 1/19/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/19/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 1/19/2024 Approved MICHEL ABAJAN
Drywall Nailing 1/23/2024 Approved MICHEL ABAJAN
Insulation 1/23/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/23/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/29/2024 Partial Inspection MICHEL ABAJAN
METHANE-Final 1/29/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Not Ready MICHEL ABAJAN
Deputy Drilled-In Anchors 2/5/2024 Conditional Approval MICHEL ABAJAN
BUILDING-Rough-Frame 4/17/2024 Approved JOHN COLEMAN
ELECTRICAL-Final 4/17/2024 Corrections Issued JOHN COLEMAN
Final 4/17/2024 Partial Inspection JOHN COLEMAN
Green Building Final 4/17/2024 Corrections Issued JOHN COLEMAN
Green Building Rough 4/17/2024 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved JOHN COLEMAN
Smoke Detectors 4/17/2024 Approved JOHN COLEMAN
Final 4/23/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Final 4/23/2024 Corrections Issued JOHN COLEMAN