13135-13137 W ALEXANDER ST 91342
Certificate Information: 13135-13137 W ALEXANDER ST 91342
- Application / Permit
- 23016-20000-35740
- Plan Check / Job No.
- B23VN14056
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 21' x 22' ATT. GARAGE TO JADU, 4' X 8' TO HALF BTHRM FOR POOL (EXT ACCESS ONLY) AND 4' x 8' PORTION TO CLOSET FOR SFD. "COMPLY WITH DEPARTMENT ORDER effective date 01/01/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2023 | SERGIO MUNIZ |
| Corrections Issued | 10/19/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 10/24/2023 | APPLICANT |
| Applicant returned to address corrections | 11/2/2023 | ANGELICA DAVE |
| Plan Check Approved | 11/7/2023 | ISIS ARGUETA |
| Issued | 11/7/2023 | APPLICANT |
| CofO in Progress | 1/16/2025 | KEVIN BERBERYAN |
| Permit Finaled | 1/28/2025 | RUBEN SALAS |
| CofO Issued | 1/28/2025 | RUBEN SALAS |
| Permit Finaled | 1/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 10/26/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 10/31/2023 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/29/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 4/29/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/12/2024 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 6/12/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Rough | 6/12/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/12/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/17/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/17/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/17/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 6/27/2024 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 7/3/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 7/3/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 7/3/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 7/3/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 9/4/2024 | Approved | JACK KARGODORIAN |
| Final | 1/14/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 1/14/2025 | Approved | KEVIN BERBERYAN |
| MERV13>=Final | 1/14/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 1/14/2025 | Approved | KEVIN BERBERYAN |