12500 N GLADSTONE AVE 91342
Certificate Information: 12500 N GLADSTONE AVE 91342
- Application / Permit
- 23016-20000-35599
- Plan Check / Job No.
- B23VN13984
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- TENANT IMPROVEMENT TO CONVERTING EXISTING SPACE INTO A CLASS 1000 CHASE AREA AND INSTALL NEW EQUIPEMENT PAD FOR ROOFTOP EQUIPMENT.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/30/2025
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | RAPHAEL ROSAS |
| Corrections Issued | 10/19/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 10/19/2023 | STEVEN KIM |
| Applicant returned to address corrections | 12/26/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/22/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/16/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 4/17/2024 | RAPHAEL ROSAS |
| Issued | 4/22/2024 | APPLICANT |
| Permit Finaled | 5/16/2025 | ANDREW DORSO |
Permit Application Clearance Information
| Green Code | Cleared | 1/11/2024 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 1/12/2024 | ROBERT PINA |
| DAS Clearance | Cleared | 2/5/2024 | Michael Perez |
| Fire Marshal Fire Life Safety | Cleared | 4/8/2024 | SARAH ZHANG |
| Chemical processes | Cleared | 4/16/2024 | SCAQMD APPROVED |
Contact Information
| Contractor | Austin Building And Design Inc; Lic. No.: 883469-B | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 5/7/2024 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 5/8/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 5/15/2024 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 5/17/2024 | Partial Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 5/20/2024 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 5/23/2024 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 6/3/2024 | Conditional Approval | ANDREW DORSO |
| Light Gage Steel Frame | 6/11/2024 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 6/11/2024 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 6/26/2024 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 6/26/2024 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 6/26/2024 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 6/27/2024 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 6/27/2024 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 7/1/2024 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 7/2/2024 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 7/3/2024 | Partial Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 7/3/2024 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 7/5/2024 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 7/8/2024 | Approved | ANDREW DORSO |
| Drywall Nailing | 7/24/2024 | Partial Inspection | ANDREW DORSO |
| Insulation | 7/24/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 7/24/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 7/26/2024 | Approved | ANDREW DORSO |
| Deputy Steel/Welding | 8/15/2024 | Conditional Approval | ANDREW DORSO |
| T-Bar Ceiling | 8/28/2024 | Partial Approval | BRIAN KELLY |
| T-Bar Ceiling | 9/26/2024 | Approved | ANDREW DORSO |
| Final | 5/16/2025 | Permit Finaled | ANDREW DORSO |
| Green Building Final | 5/16/2025 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 5/16/2025 | Approved | ANDREW DORSO |