18910-18912 W CHASE ST 91324

Certificate Information: 18910-18912 W CHASE ST 91324

Application / Permit
23016-20000-35554
Plan Check / Job No.
B23VN13957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* GROUND FLOOR ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH (E) ATTACHED JR ACCESSORY DWELLING UNIT
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
CofO Issued on 4/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/16/2023 ISIS ARGUETA
Corrections Issued 10/17/2023 ISIS ARGUETA
Applicant returned to address corrections 12/2/2023 ISIS ARGUETA
Applicant returned to address corrections 12/20/2023 ISIS ARGUETA
Applicant returned to address corrections 1/29/2024 ISIS ARGUETA
Applicant returned to address corrections 3/4/2024 SERGIO MUNIZ
Plan Check Approved 3/6/2025 VIVIAN LAO
Issued 3/10/2025 APPLICANT
CofO in Progress 3/27/2026 DAVID SCANTLIN
Permit Finaled 4/4/2026 MICHAEL PELHAM
CofO Issued 4/4/2026 MICHAEL PELHAM
Permit Finaled 4/4/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/27/2023 COLIN LOREDO
Sewer availability Cleared 10/30/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 12/7/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/23/2024 EDGAR ALCARAZ
Sewer availability Cleared 4/25/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/17/2025 Corrections Issued DAVID SCANTLIN
Green Building Rough 4/17/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 4/17/2025 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 5/6/2025 Corrections Issued KRISTEN CAUSEY
Footing/Foundation/Slab 5/16/2025 Approved KRISTEN CAUSEY
Rough-Elec/Plmb/HVAC 5/16/2025 Approved KRISTEN CAUSEY
Deputy Drilled-In Anchors 5/19/2025 Conditional Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 6/9/2025 Approved KRISTEN CAUSEY
Green Building Rough 6/9/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 6/9/2025 Approved KRISTEN CAUSEY
Shower Pan 6/9/2025 Approved KRISTEN CAUSEY
Insulation 6/10/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Approved KRISTEN CAUSEY
Drywall Nailing 6/25/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 7/9/2025 Approved KRISTEN CAUSEY
Final 7/31/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 7/31/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 7/31/2025 Approved DAVID SCANTLIN
PLUMBING-Final 7/31/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 7/31/2025 Approved DAVID SCANTLIN
ELECTRICAL-Final 8/5/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 8/5/2025 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 8/5/2025 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Not Ready KRISTEN CAUSEY
ELECTRICAL-Final 8/20/2025 Approved KRISTEN CAUSEY
Final 8/20/2025 Corrections Issued KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Approved KRISTEN CAUSEY
Final 3/26/2026 OK to Issue CofO DAVID SCANTLIN