20756 W STEPHANIE DR 91306

Certificate Information: 20756 W STEPHANIE DR 91306

Application / Permit
23016-20000-35512
Plan Check / Job No.
B23VN13939
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED 20' X 20' GARAGE & 12' X 20'-10" REC ROOM INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).
Permit Issued
Issued on 6/5/2024
Issuing Office
Current Status
CofO Issued on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 HAYATO TSUCHIYA
Corrections Issued 10/14/2023 HAYATO TSUCHIYA
Building Plans Picked Up 10/16/2023 APPLICANT
Plan Check Approved 6/5/2024 ALEC MOUSAKHANIAN
Issued 6/5/2024 APPLICANT
CofO in Progress 12/30/2024 ALEXANDER HANDY
CofO Issued 2/13/2025 JOHN JANSON
Permit Finaled 2/13/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/19/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/19/2023 BRYAN GODINEZ
Sewer availability Cleared 10/19/2023 BRYAN GODINEZ
ZI Cleared 1/2/2024 ALEX VELA
Construction within easement Cleared 6/4/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/11/2024 Approved ALEXANDER HANDY
Deputy Drilled-In Anchors 7/23/2024 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 7/23/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 7/23/2024 Partial Approval ALEXANDER HANDY
Sewer 7/23/2024 Approved ALEXANDER HANDY
Underground Mechanical 8/27/2024 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 9/10/2024 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 9/10/2024 Approved ALEXANDER HANDY
Green Building Rough 9/10/2024 Approved ALEXANDER HANDY
HVAC-Rough 9/10/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 9/10/2024 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 9/10/2024 Approved ALEXANDER HANDY
Insulation 9/13/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 9/17/2024 Approved ALEXANDER HANDY
Drywall Nailing 9/23/2024 Approved ALEXANDER HANDY
Shower Pan 9/23/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 10/11/2024 Approved SCOTT SOBEL
ELECTRICAL-Final 11/19/2024 Approved ALEXANDER HANDY
Final 11/19/2024 Corrections Issued ALEXANDER HANDY
Green Building Final 11/19/2024 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 11/19/2024 Approved ALEXANDER HANDY
PLUMBING-Final 11/19/2024 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 11/19/2024 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 11/19/2024 Approved ALEXANDER HANDY
Final 11/27/2024 Partial Approval ALEXANDER HANDY
Green Building Final 11/27/2024 Approved ALEXANDER HANDY
Final 12/31/2024 OK to Issue CofO ALEXANDER HANDY