20756 W STEPHANIE DR 91306
Certificate Information: 20756 W STEPHANIE DR 91306
- Application / Permit
- 23016-20000-35512
- Plan Check / Job No.
- B23VN13939
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED 20' X 20' GARAGE & 12' X 20'-10" REC ROOM INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 10/14/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/16/2023 | APPLICANT |
| Plan Check Approved | 6/5/2024 | ALEC MOUSAKHANIAN |
| Issued | 6/5/2024 | APPLICANT |
| CofO in Progress | 12/30/2024 | ALEXANDER HANDY |
| CofO Issued | 2/13/2025 | JOHN JANSON |
| Permit Finaled | 2/13/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 10/19/2023 | BRYAN GODINEZ |
| ZI | Cleared | 1/2/2024 | ALEX VELA |
| Construction within easement | Cleared | 6/4/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2024 | Approved | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 7/23/2024 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/23/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 7/23/2024 | Partial Approval | ALEXANDER HANDY |
| Sewer | 7/23/2024 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 8/27/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/10/2024 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/10/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 9/10/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 9/10/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/10/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 9/10/2024 | Approved | ALEXANDER HANDY |
| Insulation | 9/13/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 9/23/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 9/23/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/11/2024 | Approved | SCOTT SOBEL |
| ELECTRICAL-Final | 11/19/2024 | Approved | ALEXANDER HANDY |
| Final | 11/19/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 11/19/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 11/19/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 11/19/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 11/19/2024 | Approved | ALEXANDER HANDY |
| Final | 11/27/2024 | Partial Approval | ALEXANDER HANDY |
| Green Building Final | 11/27/2024 | Approved | ALEXANDER HANDY |
| Final | 12/31/2024 | OK to Issue CofO | ALEXANDER HANDY |