18001-18001 1/2 W OSBORNE ST 91325

Certificate Information: 18001-18001 1/2 W OSBORNE ST 91325

Application / Permit
23016-20000-35042
Plan Check / Job No.
B23VN13805
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Convert Existing Bedroom and Bathroom to (477sq.ft) JADU PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 11/16/2023
Issuing Office
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/13/2023 DAVID CASTILLO
Corrections Issued 10/15/2023 DAVID CASTILLO
Applicant returned to address corrections 11/2/2023 DAVID CASTILLO
Plan Check Approved 11/14/2023 DAVID CASTILLO
Issued 11/16/2023 APPLICANT
CofO in Progress 5/23/2024 JAVIER RAMOS JR
No Progress 6/10/2024 ROBERT GOLD
CofO in Progress 6/10/2024 ROBERT GOLD
Permit Finaled 6/21/2024 RUBEN SALAS
CofO Issued 6/21/2024 RUBEN SALAS
Permit Finaled 6/21/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/18/2023 COLIN LOREDO
Sewer availability Cleared 10/18/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/19/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Corrections Issued MISAEL ESPARZA
Underground Mechanical 1/30/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/21/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 2/21/2024 Approved JAVIER RAMOS JR
HVAC-Rough 2/21/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/21/2024 Approved JAVIER RAMOS JR
Sewer 2/29/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/5/2024 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 3/5/2024 Approved JAVIER RAMOS JR
Green Building Rough 3/5/2024 Approved JAVIER RAMOS JR
Insulation 3/12/2024 Corrections Issued JAVIER RAMOS JR
Shower Pan 3/12/2024 Approved JAVIER RAMOS JR
Insulation 3/13/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/13/2024 Approved JAVIER RAMOS JR
Drywall Nailing 3/19/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/16/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/16/2024 Approved JAVIER RAMOS JR
Final 5/16/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/16/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 5/16/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 5/16/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 5/16/2024 Approved JAVIER RAMOS JR
Final 5/22/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/22/2024 Approved JAVIER RAMOS JR