7225-7227 N KATHERINE AVE 91405
Certificate Information: 7225-7227 N KATHERINE AVE 91405
- Application / Permit
- 23016-20000-35040
- Plan Check / Job No.
- B23VN13803
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATTACHED GARGE INTO AN (E) IRREGULAR 22'-10" x 20'-6 1/2" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/7/2024
- Issuing Office
- Current Status
- CofO Issued on 9/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | ALFRED RAMIREZ |
| Corrections Issued | 10/14/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 2/19/2024 | GURUNATH NESARAJAH |
| Issued | 3/7/2024 | APPLICANT |
| CofO in Progress | 9/23/2024 | VINCENT HANLEY |
| Permit Finaled | 9/27/2024 | DANIEL ORRANTE |
| CofO Issued | 9/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/19/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 2/3/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/3/2024 | RIDWAN HARDY |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Dr Development Inc; Lic. No.: 1072452-B | 15456 VENTURA BLVD STE #302 SHERMAN OAKS, CA 91403 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/20/2024 | Conditional Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/22/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/27/2024 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 4/1/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/9/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 4/9/2024 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/12/2024 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/29/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 4/29/2024 | Approved | KIRK SANDERS |
| Green Building Final | 4/29/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 4/29/2024 | Corrections Issued | KIRK SANDERS |
| Insulation | 4/29/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 4/29/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 5/13/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/13/2024 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/13/2024 | Approved | VINCENT HANLEY |
| Insulation | 5/15/2024 | Corrections Issued | VINCENT HANLEY |
| Drywall Nailing | 6/7/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/7/2024 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 6/7/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/12/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 6/12/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | VINCENT HANLEY |
| Final | 9/6/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 9/6/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 9/6/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/6/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/18/2024 | Approved | VINCENT HANLEY |
| Final | 9/18/2024 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 9/18/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/18/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/18/2024 | Approved | VINCENT HANLEY |