3850 S FIGUEROA ST 90037
Certificate Information: 3850 S FIGUEROA ST 90037
- Application / Permit
- 23016-20000-34944
- Plan Check / Job No.
- B23VN13780
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Car Sales - new
- Work Description
- ePlan: Change of use from Restaurant to New Automobile Sales Office . No change in parking .
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Current Status
- Issued on 2/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | GEORGE ALVAREZ |
| Corrections Issued | 10/16/2023 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 1/11/2024 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/22/2024 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/30/2024 | FERNANDO FLORES |
| Plan Check Approved | 2/25/2024 | ZAW HAN |
| Issued | 2/26/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/24/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2023 | AMBER CAMPBELL |
| Historic Resource Verification | Cleared | 11/2/2023 | RAFAEL FONTES |
| Comm Cor/Mini-Mall | Cleared | 1/10/2024 | RUBEN VASQUEZ |
| Comm Cor/Mini-Mall | Cleared | 1/10/2024 | RUBEN VASQUEZ |
| Comm Cor/Mini-Mall | Cleared | 1/10/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 1/10/2024 | RUBEN VASQUEZ |
| Redevelopment Project Area | Cleared | 1/31/2024 | YASMINE BASHIRI |
Contact Information
| Architect | Yelos-San, Martin, Miguel Santiago; Lic. No.: NA22548 | , |
| Contractor | Kunzik & Sara Construction Inc; Lic. No.: 847939-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 6/18/2024 | OK for TCO | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 6/18/2024 | Approved | ALFREDO LOPEZ |
| Wood Frame | 6/18/2024 | Approved | ALFREDO LOPEZ |