12827 W VICTORY BLVD 91606
Certificate Information: 12827 W VICTORY BLVD 91606
- Application / Permit
- 23016-20000-34462
- Plan Check / Job No.
- B23VN13640
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (21) Theater
- Work Description
- Tenant improvement to existing cinema auditorium 7 interior only. Replace existing recliner seats, replace screen, add stage, modify exit door for auditorium 7, add new wall speakers, and add new wall finishes.
- Permit Issued
- Issued on 9/26/2024
- Issuing Office
- Current Status
- Permit Finaled on 12/13/2024
Permit Application Status History
| Submitted | 10/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 10/16/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/20/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/27/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 6/4/2024 | SERGIO GUTIERREZ |
| Issued | 9/26/2024 | APPLICANT |
| Permit Finaled | 12/13/2024 | KENNETH ROBERTS |
Permit Application Clearance Information
| Green Code | Cleared | 3/1/2024 | MICHAEL AYERS |
| "Q" conditions | Cleared | 3/6/2024 | ALEX VELA |
| Miscellaneous | Cleared | 3/6/2024 | ALEX VELA |
| Miscellaneous | Cleared | 3/6/2024 | ALEX VELA |
| Miscellaneous | Cleared | 3/6/2024 | ALEX VELA |
| ZA Case | Cleared | 3/6/2024 | ALEX VELA |
| ZA Case | Cleared | 3/6/2024 | ALEX VELA |
| ZA Case | Cleared | 3/6/2024 | ALEX VELA |
| ZA Case | Cleared | 3/6/2024 | ALEX VELA |
| DAS Clearance | Cleared | 3/11/2024 | Rosendo Medina |
| Fire Marshal Fire Life Safety | Cleared | 5/16/2024 | FIRE DEPARTMENT |
Contact Information
| Contractor | Moorefield Construction Inc; Lic. No.: 397892-B | 600 N TUSTIN AVENUE SUITE #210 SANTA ANA, CA 92705 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/4/2024 | Corrections Issued | STEVEN LEVITT |
| Light Gage Steel Frame | 10/17/2024 | Approved | STEVEN LEVITT |
| Drywall Nailing | 10/21/2024 | Approved | STEVEN LEVITT |
| Partition/T-Bar Ceiling | 10/25/2024 | Approved | STEVEN LEVITT |
| Final | 12/11/2024 | Corrections Issued | ANDREW DORSO |
| Green Building Final | 12/11/2024 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 12/11/2024 | Not Ready for Inspection | ANDREW DORSO |
| Final | 12/13/2024 | Permit Finaled | KENNETH ROBERTS |
| Smoke Detectors | 12/13/2024 | Approved | KENNETH ROBERTS |