8034 N RHODES AVE 91605
Certificate Information: 8034 N RHODES AVE 91605
- Application / Permit
- 23016-20000-34366
- Plan Check / Job No.
- B23VN13616
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) WITH (E) ATTACHED STORAGE
- Permit Issued
- Issued on 6/12/2024
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2023 | ALFRED RAMIREZ |
| Corrections Issued | 11/9/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 3/7/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 3/19/2024 | JOSEPH RAFOLS |
| Issued | 6/12/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | MATTHEW NELSON |
| CofO Issued | 10/16/2025 | RUBEN SALAS |
| Permit Finaled | 10/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/26/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Spacex Construction Inc; Lic. No.: 1033768-B | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/24/2024 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/27/2024 | Approved | MATTHEW NELSON |
| Underground Mechanical | 6/27/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/5/2024 | Approved | MATTHEW NELSON |
| Underground Mechanical | 7/5/2024 | Approved | MATTHEW NELSON |
| Underground Mechanical | 7/22/2024 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 9/16/2024 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 9/16/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/24/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/4/2024 | Approved | MATTHEW NELSON |
| Insulation | 10/4/2024 | Approved | MATTHEW NELSON |
| Pre-Inspection | 10/16/2024 | Partial Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/18/2024 | Partial Approval | WILLIAM WREN |
| Drywall Nailing | 10/29/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/24/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 3/24/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 6/30/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 6/30/2025 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 6/30/2025 | Approved | MATTHEW NELSON |
| Final | 8/12/2025 | No Access for Inspection | MATTHEW NELSON |
| Final | 9/3/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 9/8/2025 | OK to Issue CofO | MATTHEW NELSON |
| Final | 9/22/2025 | Partial Approval | DAVID MATSON |