10128 N LEMONA AVE 91345
Certificate Information: 10128 N LEMONA AVE 91345
- Application / Permit
- 23016-20000-34034
- Plan Check / Job No.
- B23VN13472
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW PATIO COVER TO (E) SINGLE FAMILY DWELLING. CONVERT (E) ENCLOSED PATIO TO (N) BEDROOM WITH CLOSET AND BATHROOM AND LAUNDRY.
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 10/5/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 11/7/2023 | KAMYAR EMAMI |
| Applicant returned to address corrections | 11/28/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 12/12/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 1/23/2024 | GIOVANNY CHAVEZ |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 6/5/2024 | ROBERT GOLD |
| Permit Finaled | 6/5/2024 | RUBEN SALAS |
| CofO Issued | 6/5/2024 | RUBEN SALAS |
| Permit Finaled | 6/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/13/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/2/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/30/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 1/30/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/13/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/15/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/15/2024 | Approved | MICHEL ABAJAN |
| Insulation | 2/15/2024 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 2/20/2024 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 2/22/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/22/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 2/26/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/27/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/11/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/11/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/9/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/9/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/9/2024 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 4/9/2024 | Approved | JENNIFER RABUCHIN |
| Final | 5/22/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 5/22/2024 | Corrections Issued | JOHN COLEMAN |
| Final | 6/4/2024 | OK to Issue CofO | ROBERT GOLD |
| Green Building Final | 6/4/2024 | Approved | ROBERT GOLD |