13172-13174 W BRYSON ST 91331
Certificate Information: 13172-13174 W BRYSON ST 91331
- Application / Permit
- 23016-20000-33968
- Plan Check / Job No.
- B23VN13454
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATT GARAGE TO (N) 363 SF ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2023 | SERGIO MUNIZ |
| Corrections Issued | 10/7/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 10/11/2023 | APPLICANT |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 7/22/2025 | VINCENT HANLEY |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
| CofO Issued | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/1/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/13/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/18/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/18/2025 | Partial Approval | VINCENT HANLEY |
| Sewer | 3/18/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/4/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/4/2025 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 4/14/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 4/24/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/24/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/24/2025 | Approved | VINCENT HANLEY |
| Insulation | 4/24/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/30/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/30/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 4/30/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/3/2025 | Approved | VINCENT HANLEY |
| Final | 7/3/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/3/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/3/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/3/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/3/2025 | Approved | VINCENT HANLEY |
| Final | 7/22/2025 | OK to Issue CofO | VINCENT HANLEY |