1369-1369 1/2 E 21ST ST 90011
Certificate Information: 1369-1369 1/2 E 21ST ST 90011
- Application / Permit
- 23016-20000-33521
- Plan Check / Job No.
- B23VN13287
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Eplan: Remodel of (E) 2-Story Duplex, Remodel to Included Replacement of Damaged Roof Sheathing, Asphalt Shingles , Roof Framing, Drywall , Insulation , Stucco , and -Replace Damaged Windows and Doors: Replace Like for Like 4 Doors and 5 Windows
- Permit Issued
- Issued on 1/15/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/28/2025
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | DAVID CASTILLO |
| Corrections Issued | 10/15/2023 | DAVID CASTILLO |
| Plan Check Approved | 11/13/2023 | DAVID CASTILLO |
| Issued | 1/15/2024 | APPLICANT |
| Permit Finaled | 8/27/2025 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | H P Associates Inc; Lic. No.: 740238-B | , |
| Engineer | So,, Anson; Lic. No.: C70444 | 83 DEVONSHIRE IRVINE, CA 92620 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 8/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/14/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 9/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 9/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/1/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/1/2024 | Approved | ALEX COLIN |
| Pre-Inspection | 3/20/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/4/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 8/4/2025 | Approved | BARRY HACHE |
| Final | 8/27/2025 | Permit Finaled | ALEJANDRO DE ARTOLA |