4203 S HOOVER ST 90037
Certificate Information: 4203 S HOOVER ST 90037
- Application / Permit
- 23016-20000-33508
- Plan Check / Job No.
- B23VN13281
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- T.I. & Change of use from retail to Dental office & restripe parking area
- Permit Issued
- Issued on 12/3/2023
- Issuing Office
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | SEAN SHAHMIRI |
| Corrections Issued | 10/10/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 10/10/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/27/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 11/20/2023 | SEAN SHAHMIRI |
| Issued | 12/3/2023 | APPLICANT |
| CofO in Progress | 8/22/2024 | DARRYL ARNOLD |
| CofO Issued | 8/23/2024 | ERNESTO CORRAL |
| Permit Finaled | 8/23/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 10/23/2023 | Rosendo Medina |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 10/31/2023 | JUSTIN BICOL |
| Community Plan Implem. Overlay | Cleared | 11/16/2023 | MANERI ROMAN |
Contact Information
| Architect | Miguel,, Miguel Maximo; Lic. No.: C13612 | 2214 GRAFTON STREET SIMI VALLEY, CA 93063 |
| Contractor | J C Galvan Company Inc; Lic. No.: 1021270-B | 7056 FORBES AVE VAN NUYS, CA 91406 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/28/2024 | Partial Approval | ALFREDO LOPEZ |
| Pre-Inspection | 3/28/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 5/1/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 5/7/2024 | Partial Approval | ALFREDO LOPEZ |
| T-Bar Ceiling | 5/20/2024 | Partial Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 6/21/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 8/12/2024 | Partial Approval | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 8/12/2024 | Approved | ALFREDO LOPEZ |
| Final | 8/16/2024 | OK to Issue CofO | DARRYL ARNOLD |
| Special/Order Compliance | 8/21/2024 | Corrections Issued | DARRYL ARNOLD |