7511-7513 N TOPEKA DR 91335

Certificate Information: 7511-7513 N TOPEKA DR 91335

Application / Permit
23016-20000-33403
Plan Check / Job No.
B23VN13224
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX ATT 20'3" X 18'3" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e).
Permit Issued
Issued on 10/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2023 APPLICANT
Assigned to Plan Check Engineer 9/29/2023 HAYATO TSUCHIYA
Corrections Issued 9/30/2023 HAYATO TSUCHIYA
Building Plans Picked Up 10/2/2023 APPLICANT
Plan Check Approved 10/19/2023 MIROOSH KHACHATOORIAN
Issued 10/26/2023 APPLICANT
CofO in Progress 3/19/2026 ARUTYUN MADATYAN
Permit Finaled 3/20/2026 JOHN JANSON
CofO Issued 3/20/2026 JOHN JANSON
Permit Finaled 3/20/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/7/2023 CARLOS AGUILERA
Sewer availability Cleared 10/7/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/18/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 8/6/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 8/6/2025 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 8/8/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 8/8/2025 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 8/12/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 8/12/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 8/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 8/29/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 8/29/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 9/8/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 9/8/2025 Approved ARUTYUN MADATYAN
Green Building Rough 9/8/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 9/8/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 9/8/2025 Partial Approval ARUTYUN MADATYAN
Sewer 9/8/2025 Not Ready for Inspection ARUTYUN MADATYAN
Insulation 9/12/2025 Approved ARUTYUN MADATYAN
Sewer 9/12/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 9/17/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval ARUTYUN MADATYAN
Shower Pan 9/17/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 9/19/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 3/10/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 3/10/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 3/10/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 3/10/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 3/10/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 3/10/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/13/2026 Approved ARUTYUN MADATYAN
Final 3/13/2026 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 3/13/2026 Approved ARUTYUN MADATYAN
HVAC-Final 3/13/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 3/13/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved ARUTYUN MADATYAN
Final 3/18/2026 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 3/18/2026 Approved ARUTYUN MADATYAN