7511-7513 N TOPEKA DR 91335
Certificate Information: 7511-7513 N TOPEKA DR 91335
- Application / Permit
- 23016-20000-33403
- Plan Check / Job No.
- B23VN13224
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX ATT 20'3" X 18'3" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e).
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 9/30/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/2/2023 | APPLICANT |
| Plan Check Approved | 10/19/2023 | MIROOSH KHACHATOORIAN |
| Issued | 10/26/2023 | APPLICANT |
| CofO in Progress | 3/19/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 3/20/2026 | JOHN JANSON |
| CofO Issued | 3/20/2026 | JOHN JANSON |
| Permit Finaled | 3/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/7/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 8/6/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/6/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 8/8/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/8/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 8/12/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/12/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 8/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Partial Approval | ARUTYUN MADATYAN |
| HVAC-Rough | 8/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/29/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 9/8/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 9/8/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 9/8/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 9/8/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 9/8/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 9/8/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Insulation | 9/12/2025 | Approved | ARUTYUN MADATYAN |
| Sewer | 9/12/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 9/17/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 9/17/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 9/19/2025 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 3/10/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 3/10/2026 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 3/10/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 3/10/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/10/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 3/10/2026 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/13/2026 | Approved | ARUTYUN MADATYAN |
| Final | 3/13/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 3/13/2026 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 3/13/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/13/2026 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Approved | ARUTYUN MADATYAN |
| Final | 3/18/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 3/18/2026 | Approved | ARUTYUN MADATYAN |