23413-23415 W WINDOM ST 91304

Certificate Information: 23413-23415 W WINDOM ST 91304

Application / Permit
23016-20000-33333
Plan Check / Job No.
B23VN13178
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22.
Permit Issued
Issued on 10/10/2023
Issuing Office
Valley
Current Status
Issued on 10/10/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/27/2023 APPLICANT
Assigned to Plan Check Engineer 9/27/2023 MIROOSH KHACHATOORIAN
Corrections Issued 9/27/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 10/10/2023 PINANK PATEL
Issued 10/10/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/30/2023 CARLOS AGUILERA
Sewer availability Cleared 9/30/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/2/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/14/2023 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/14/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 12/14/2023 Approved CHRIS CHRISTENSEN
Pre-Inspection 12/14/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/22/2023 No Access for Inspection CHRIS CHRISTENSEN
Insulation 12/22/2023 No Access for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/26/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 12/26/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/26/2023 Approved CHRIS CHRISTENSEN
Insulation 12/26/2023 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/28/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 1/2/2024 No Access for Inspection CHRIS CHRISTENSEN
Drywall Nailing 1/4/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Final 1/22/2026 Approved CHRIS CHRISTENSEN
Final 1/22/2026 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 1/22/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Final 1/22/2026 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/22/2026 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 1/22/2026 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 3/27/2026 Approved CHRIS CHRISTENSEN
Final 3/27/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 3/27/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Final 3/27/2026 Approved CHRIS CHRISTENSEN