19217 W KESWICK ST 91335

Certificate Information: 19217 W KESWICK ST 91335

Application / Permit
23016-20000-33185
Plan Check / Job No.
B23VN13126
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER ENGINEER.
Permit Issued
Issued on 11/29/2023
Issuing Office
Current Status
CofO Issued on 11/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2023 APPLICANT
Assigned to Plan Check Engineer 9/29/2023 SERGIO MUNIZ
Corrections Issued 10/2/2023 SERGIO MUNIZ
Building Plans Picked Up 10/3/2023 APPLICANT
Applicant returned to address corrections 11/6/2023 DANIEL ABRAMYAN
Plan Check Approved 11/29/2023 ROSENDO MEDINA
Issued 11/29/2023 APPLICANT
CofO in Progress 11/7/2024 ARUTYUN MADATYAN
Permit Finaled 11/12/2024 JOHN JANSON
CofO Issued 11/12/2024 JOHN JANSON
Permit Finaled 11/12/2024 JOHN JANSON

Permit Application Clearance Information

Tract Map conditions Cleared 10/5/2023 STEVEN WECHSLER
Address approval Cleared 10/6/2023 NIKKI ZULUETA
Sewer availability Cleared 10/6/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/10/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2024 Corrections Issued HENRY KIM
PLUMBING-Rough 3/8/2024 Partial Approval HENRY KIM
Deputy Drilled-In Anchors 3/13/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 3/18/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 5/30/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 5/30/2024 Approved JEFFREY BULL
Green Building Rough 5/30/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 5/30/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 6/10/2024 Not Ready for Inspection HENRY KIM
Green Building Rough 6/10/2024 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 6/10/2024 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 6/18/2024 Partial Approval JEFFREY BULL
Insulation 6/28/2024 Approved HENRY KIM
BUILDING-Rough-Frame 7/11/2024 Approved JEFFREY BULL
Green Building Rough 7/11/2024 Approved JEFFREY BULL
Drywall Nailing 7/17/2024 Not Ready for Inspection HENRY KIM
Drywall Nailing 7/19/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 8/14/2024 Approved JEFFREY BULL
Special/Order Compliance 8/14/2024 Approved SCOTT SOBEL
Final 10/11/2024 Corrections Issued JEFFREY BULL
Green Building Final 10/11/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 10/11/2024 Approved JEFFREY BULL
ELECTRICAL-Final 11/6/2024 Approved ARUTYUN MADATYAN
Final 11/6/2024 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 11/6/2024 Approved ARUTYUN MADATYAN
HVAC-Final 11/6/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 11/6/2024 Approved ARUTYUN MADATYAN