10126-10128 N LEMONA AVE 91345
Certificate Information: 10126-10128 N LEMONA AVE 91345
- Application / Permit
- 23016-20000-32659
- Plan Check / Job No.
- B23VN12979
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing atached garage to ADU per LAMC 12.22 A.33(c) and (e). Design per WFPP.
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | CAROLEAN BASMA |
| Corrections Issued | 9/29/2023 | CAROLEAN BASMA |
| Plan Check Approved | 10/11/2023 | CAROLEAN BASMA |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 3/20/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 3/26/2024 | RUBEN SALAS |
| CofO Issued | 3/26/2024 | RUBEN SALAS |
| Permit Finaled | 3/26/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 10/2/2023 | GABRIELLA TORRES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/17/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 10/17/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 10/17/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Underground Mechanical | 10/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/8/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 11/8/2023 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 11/8/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 11/8/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/13/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 11/13/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/13/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/16/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/16/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/20/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/20/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 11/27/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/7/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/7/2023 | Approved | MISAEL ESPARZA |
| Sewer | 12/19/2023 | Approved | JOHN COLEMAN |
| Underground Mechanical | 12/19/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 3/7/2024 | Approved | DAVID ANDERSON |
| Final | 3/7/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 3/7/2024 | Corrections Issued | DAVID ANDERSON |
| HVAC-Final | 3/7/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 3/7/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 3/7/2024 | Approved | DAVID ANDERSON |
| Final | 3/20/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 3/20/2024 | Approved | JENNIFER RABUCHIN |