10505 W CALIFA ST 91601
Certificate Information: 10505 W CALIFA ST 91601
- Application / Permit
- 23016-20000-32468
- Plan Check / Job No.
- B23VN12892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/25/2024
- Issuing Office
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 9/27/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 1/23/2024 | GIOVANNY CHAVEZ |
| Issued | 1/25/2024 | APPLICANT |
| CofO in Progress | 8/2/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
| CofO Issued | 8/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 9/27/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2023 | COLIN LOREDO |
| Construction near power lines | Cleared | 1/19/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/19/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/7/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/7/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/7/2024 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 3/7/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/28/2024 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 3/28/2024 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/28/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/4/2024 | Partial Approval | JOHN HAYES |
| Green Building Rough | 4/4/2024 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 4/4/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/22/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/22/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/23/2024 | No Access for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 5/1/2024 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Approved | JOHN COLEMAN |
| Shower Pan | 5/1/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Drywall Nailing | 5/3/2024 | Approved | LEONARD ROSS II |
| Interior/Exterior Lathing | 5/3/2024 | Approved | LEONARD ROSS II |
| Shower Pan | 5/3/2024 | Approved | LEONARD ROSS II |
| ELECTRICAL-Final | 6/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/28/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 6/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 6/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 6/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 6/28/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/2/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 8/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |