10100 W RIVERSIDE DR 91602

Certificate Information: 10100 W RIVERSIDE DR 91602

Application / Permit
23016-20000-32298
Plan Check / Job No.
B23VN12822
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bank
Work Description
REMODEL FIRST FLOOR OF EXISTING 2-STORY BANK (3554SF). NO WORK ON SECOND FLOOR
Permit Issued
Issued on 8/12/2024
Issuing Office
Current Status
Permit Finaled on 6/9/2025

Permit Application Status History

Submitted 9/28/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 CAROLYNN NEPOMUCENO
Corrections Issued 10/5/2023 CAROLYNN NEPOMUCENO
Quality Review Completed 10/11/2023 EUGENE BARBEAU
Plan Check Approved 2/20/2024 CAROLYNN NEPOMUCENO
Issued 8/12/2024 APPLICANT
Permit Finaled 6/9/2025 KENNETH ROBERTS

Permit Application Clearance Information

"Q" conditions Cleared 10/18/2023 NELSON RODRIGUEZ
Green Code Cleared 2/6/2024 MICHAEL AYERS
DAS Clearance Cleared 2/7/2024 Pinank Patel

Contact Information

Architect Klopfer,, Scott Merrill; Lic. No.: C38207 21145 QUAY STREET NW      OAK GROVE, MN 55303
Contractor Construction Resources Inc; Lic. No.: 920616-B       ,
Engineer Brown,, Kelsey; Lic. No.: C91203 2300 BERKSHIRE LANE N SUITE 200      PLYMOUTH, MN 55441

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 11/4/2024 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 11/4/2024 Partial Inspection ROBERT DAVIS
Light Gage Steel Frame 11/5/2024 Not Ready for Inspection STEVEN LEVITT
Drywall Nailing 11/8/2024 Partial Approval STEVEN LEVITT
T-Bar Ceiling 11/21/2024 Approved STEVEN LEVITT
Light Gage Steel Frame 12/20/2024 Not Ready for Inspection STEVEN LEVITT
Light Gage Steel Frame 12/23/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 12/27/2024 Partial Approval JOHN KITCKO
Drywall Nailing 1/10/2025 Partial Approval KENNETH ROBERTS
Deputy Drilled-In Anchors 1/22/2025 Conditional Approval STEVEN LEVITT
Light Gage Steel Frame 2/3/2025 Not Ready for Inspection STEVEN LEVITT
Light Gage Steel Frame 2/5/2025 Approved STEVEN LEVITT
Drywall Nailing 2/6/2025 Corrections Issued STEVEN LEVITT
Drywall Nailing 2/12/2025 Approved STEVEN LEVITT
Final 6/5/2025 Not Ready for Inspection DANIEL VARNUM
Green Building Final 6/5/2025 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 6/5/2025 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 6/5/2025 Not Ready for Inspection DANIEL VARNUM
Final 6/9/2025 Permit Finaled KENNETH ROBERTS
Green Building Final 6/9/2025 Approved KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV No Gas KENNETH ROBERTS
Smoke Detectors 6/9/2025 Approved KENNETH ROBERTS