6324 N CAMELLIA AVE 91606

Certificate Information: 6324 N CAMELLIA AVE 91606

Application / Permit
23016-20000-32000
Plan Check / Job No.
B23VN12714
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING RECREATION ROOM INTO A DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 11/2/2023
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 GIOVANNY CHAVEZ
Corrections Issued 9/25/2023 GIOVANNY CHAVEZ
Plan Check Approved 10/26/2023 GIOVANNY CHAVEZ
Issued 11/2/2023 APPLICANT
CofO in Progress 2/14/2025 JOSE AVILA
Permit Finaled 3/13/2025 RUBEN SALAS
CofO Issued 3/13/2025 RUBEN SALAS
Permit Finaled 3/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/10/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/10/2023 COLIN LOREDO
Sewer availability Cleared 10/10/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: NA93320       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/15/2023 No Access for Inspection JOHN HAYES
Pre-Inspection 12/1/2023 Approved JOHN HAYES
Final 2/2/2024 Corrections Issued JOHN HAYES
Pre-Inspection 5/1/2024 Corrections Issued JOSE AVILA
Pre-Inspection 7/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 7/12/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 8/26/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 8/26/2024 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 8/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 8/29/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 12/4/2024 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 12/4/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 1/3/2025 Approved JOSE AVILA
HVAC-Rough 1/3/2025 Approved JOSE AVILA
PLUMBING-Rough 1/3/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 1/30/2025 Approved JACK KARGODORIAN
Final 1/30/2025 Corrections Issued JACK KARGODORIAN
Smoke Detectors 1/30/2025 Approved JACK KARGODORIAN
Final 2/13/2025 OK to Issue CofO JOSE AVILA
Service/Power Release 2/26/2025 Approved JOSE AVILA