8481 N CANTERBURY AVE 91352
Certificate Information: 8481 N CANTERBURY AVE 91352
- Application / Permit
- 23016-20000-31976
- Plan Check / Job No.
- B23VN12704
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- CofO Issued on 4/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 10/5/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 3/15/2024 | PINANK PATEL |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 4/23/2025 | VINCENT HANLEY |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
| CofO Issued | 4/29/2025 | RUBEN SALAS |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/13/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 2/14/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/14/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 7/12/2024 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 7/17/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 7/18/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/24/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/24/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/24/2024 | Approved | VINCENT HANLEY |
| Insulation | 9/24/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 9/24/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/1/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 10/7/2024 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 10/7/2024 | Approved | DAVID MATSON |
| Underground Mechanical | 11/5/2024 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 11/8/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 11/14/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 11/14/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 11/25/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | DAVID MATSON |
| Final | 4/10/2025 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 4/10/2025 | Approved | DAVID MATSON |
| HVAC-Final | 4/10/2025 | Approved | DAVID MATSON |
| PLUMBING-Final | 4/10/2025 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 4/10/2025 | Corrections Issued | DAVID MATSON |
| ELECTRICAL-Final | 4/22/2025 | Approved | VINCENT HANLEY |
| Final | 4/22/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 4/22/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/22/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 4/22/2025 | Approved | VINCENT HANLEY |