243-245 1/4 E 84TH ST 90003
Certificate Information: 243-245 1/4 E 84TH ST 90003
- Application / Permit
- 23016-20000-31923
- Plan Check / Job No.
- B23VN12686
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: CONVERT ATTACHED GARAGE AND STORAGE ROOM ON 1ST FLOOR TO ADU PER GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2023 | JOHNPAUL ISIP |
| Corrections Issued | 9/25/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 10/31/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 11/16/2023 | CAROLEAN BASMA |
| Plan Check Approved | 1/8/2024 | CAROLEAN BASMA |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 9/19/2025 | MICHAEL LEWIS |
| Permit Finaled | 9/19/2025 | DEROLD HAUFF |
| CofO Issued | 9/19/2025 | DEROLD HAUFF |
| Permit Finaled | 9/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2023 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/29/2023 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2023 | ERIK BEASLEY |
| Tenant Habitability Plan | Cleared | 12/28/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Corrections Issued | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 4/22/2024 | Conditional Approval | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 4/30/2024 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/2/2024 | Partial Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/30/2024 | Partial Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/3/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/28/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/8/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 8/8/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/12/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/30/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 8/30/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/10/2024 | No Access for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 9/10/2024 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/20/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Corrections Issued | MICHAEL LEWIS |
| Insulation | 9/20/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/20/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/4/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 10/17/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 10/17/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/5/2024 | Partial Approval | JOSH MEISTER |
| Insulation | 11/14/2024 | No Access for Inspection | ALEX COLIN |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 11/18/2024 | Approved | MICHAEL LEWIS |
| Insulation | 12/2/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Insulation | 12/5/2024 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 12/13/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 12/30/2024 | Approved | JOHN QUINTANILLA |
| Gas Test | 3/25/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Gas Test | 4/1/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Gas Test | 4/11/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Gas Test | 4/17/2025 | Approved | JOHN QUINTANILLA |
| Final | 5/30/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Green Building Final | 5/30/2025 | No Access for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 5/30/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Final | 6/6/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 6/6/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 6/6/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 6/13/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Green Building Final | 6/13/2025 | No Access for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 6/13/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Final | 6/20/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 6/20/2025 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 6/20/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 7/2/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 7/2/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Green Building Final | 7/18/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Final | 7/23/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 7/23/2025 | Partial Inspection | JOHN QUINTANILLA |
| Final | 8/4/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Final | 8/4/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 8/4/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 8/4/2025 | Approved | JOHN QUINTANILLA |
| Final | 8/12/2025 | Conditional Approval | JOHN QUINTANILLA |
| Final | 9/19/2025 | OK to Issue CofO | MICHAEL LEWIS |