13210 W OTSEGO ST 91423

Certificate Information: 13210 W OTSEGO ST 91423

Application / Permit
23016-20000-31878
Plan Check / Job No.
B23VN12662
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED RECREATION ROOM AND GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 1/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 JEROME MAGAT PALMA
Corrections Issued 9/22/2023 JEROME MAGAT PALMA
Building Plans Picked Up 9/25/2023 APPLICANT
Plan Check Approved 1/12/2024 GIOVANNY CHAVEZ
Issued 1/23/2024 APPLICANT
CofO in Progress 5/16/2025 OGANES TARAKHCHYAN
Permit Finaled 5/27/2025 RUBEN SALAS
CofO Issued 5/27/2025 RUBEN SALAS
Permit Finaled 5/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/30/2023 CARLOS AGUILERA
Sewer availability Cleared 9/30/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/4/2023 CARLOS AGUILERA
Construction near power lines Cleared 1/6/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: C69935 16873 MCKEEVER ST      GRANADA HILLS, CA 91344

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/26/2024 Corrections Issued JOSE AVILA
Sewer 2/26/2024 Approved JOSE AVILA
Deputy Drilled-In Anchors 3/8/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/11/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/18/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 5/10/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/10/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 5/10/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/10/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/15/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 5/15/2024 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 5/31/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 5/31/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 5/31/2024 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/24/2024 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 6/24/2024 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 6/24/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 6/24/2024 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 7/15/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 7/15/2024 Approved KEVIN BERBERYAN
HVAC-Rough 7/15/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 7/15/2024 Partial Approval KEVIN BERBERYAN
Insulation 9/3/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/3/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 9/3/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 9/25/2024 Approved MICHAEL CORTEZ
Green Building Final 3/18/2025 No Access for Inspection OGANES TARAKHCHYAN
Green Building Rough 3/18/2025 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 3/18/2025 No Access for Inspection OGANES TARAKHCHYAN
Pre-Inspection 3/19/2025 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/10/2025 Approved OGANES TARAKHCHYAN
Final 4/10/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/10/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 4/10/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 4/10/2025 Approved OGANES TARAKHCHYAN
Final 4/16/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 5/15/2025 OK to Issue CofO OGANES TARAKHCHYAN