754 E 84TH PL #1-5 90001

Certificate Information: 754 E 84TH PL #1-5 90001

Application / Permit
23016-20000-31794
Plan Check / Job No.
B23VN12620
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN CONVERT (E) ATTACHED GARAGE TO (N) ATTACHED ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 2/13/2024
Issuing Office
Current Status
Issued on 2/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/22/2023 ALEC MOUSAKHANIAN
Corrections Issued 9/23/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 11/1/2023 ALEC MOUSAKHANIAN
Plan Check Approved 1/13/2024 ALEC MOUSAKHANIAN
Issued 2/13/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 10/3/2023 DAVID LOPEZ
Address approval Cleared 11/8/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 11/8/2023 DAVID LOPEZ
Roof/Waste drainage to street Cleared 11/8/2023 DAVID LOPEZ
Construction near power lines Cleared 12/15/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/6/2024 Conditional Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 3/6/2024 Not Ready for Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 3/6/2024 Not Ready for Inspection ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 4/5/2024 Approved DARRYL ARNOLD
Footing/Foundation/Slab 4/5/2024 Approved DARRYL ARNOLD
Green Building Rough 7/19/2024 Conditional Approval DARRYL ARNOLD
Wood Frame 7/19/2024 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 2/6/2025 Approved DARRYL ARNOLD
Insulation 2/13/2025 Approved DARRYL ARNOLD
Drywall Nailing 2/19/2025 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 2/19/2025 Approved ALFREDO LOPEZ
Final 4/25/2025 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 4/25/2025 Approved DARRYL ARNOLD
Green Building Rough 4/25/2025 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 4/25/2025 Corrections Issued DARRYL ARNOLD
Wood Frame 4/25/2025 Not Ready for Inspection DARRYL ARNOLD
Final 8/28/2025 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 8/28/2025 Approved DARRYL ARNOLD
Wood Frame 8/28/2025 Approved DARRYL ARNOLD