10941-10943 N GOTHIC AVE 91344

Certificate Information: 10941-10943 N GOTHIC AVE 91344

Application / Permit
23016-20000-31775
Plan Check / Job No.
B23VN12613
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Conversion of (E) attached garage into a ADU PER STATE LAW All work per WFPP.
Permit Issued
Issued on 3/5/2024
Issuing Office
Current Status
CofO Issued on 12/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2023 APPLICANT
Assigned to Plan Check Engineer 9/20/2023 MICHAEL LANZONE
Corrections Issued 9/21/2023 MICHAEL LANZONE
Applicant returned to address corrections 10/17/2023 ADAM HEGAZI
Applicant returned to address corrections 1/18/2024 KHUONG TRUONG
Applicant returned to address corrections 1/19/2024 KHUONG TRUONG
Applicant returned to address corrections 2/17/2024 KHUONG TRUONG
Plan Check Approved 3/5/2024 KHUONG TRUONG
Issued 3/5/2024 APPLICANT
CofO in Progress 12/17/2024 ROBERT GOLD
Permit Finaled 12/19/2024 RUBEN SALAS
CofO Issued 12/19/2024 RUBEN SALAS
Permit Finaled 12/19/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/1/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 3/1/2024 EDGAR ALCARAZ
Sewer availability Cleared 3/1/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/8/2024 Approved JAVIER RAMOS JR
Sewer 5/23/2024 Not Ready for Inspection LEONARD ROSS II
Underground Mechanical 5/23/2024 Partial Approval LEONARD ROSS II
Deputy Drilled-In Anchors 5/24/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/30/2024 Approved JAVIER RAMOS JR
Sewer 5/30/2024 Approved JAVIER RAMOS JR
Wood Frame 6/12/2024 Partial Inspection JAVIER RAMOS JR
Wood Frame 6/27/2024 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 6/28/2024 Conditional Approval JAVIER RAMOS JR
ELECTRICAL-Rough 7/11/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/30/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 7/30/2024 Corrections Issued JAVIER RAMOS JR
Shower Pan 7/30/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Approved JAVIER RAMOS JR
Insulation 8/8/2024 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 8/8/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 8/8/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/23/2024 Approved JAVIER RAMOS JR
Drywall Nailing 8/23/2024 Approved JAVIER RAMOS JR
Green Building Rough 8/23/2024 Approved JAVIER RAMOS JR
HVAC-Rough 8/23/2024 Partial Inspection JAVIER RAMOS JR
MERV13>=Rough 8/23/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/30/2024 No Access for Inspection MATTHEW NELSON
ELECTRICAL-Final 11/1/2024 Corrections Issued JAVIER RAMOS JR
Final 11/8/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/8/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 11/8/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 11/8/2024 Not Ready for Inspection JENNIFER RABUCHIN
Final 11/15/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 11/15/2024 Approved JACK KARGODORIAN
Smoke Detectors 11/15/2024 Approved JACK KARGODORIAN
ELECTRICAL-Final 11/20/2024 Approved JAVIER RAMOS JR
Final 11/20/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Final 11/20/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 11/20/2024 Approved JAVIER RAMOS JR
Service/Power Release 11/20/2024 Approved JAVIER RAMOS JR
Final 12/17/2024 OK to Issue CofO ROBERT GOLD