222 1/8 W 66TH ST 90003
Certificate Information: 222 1/8 W 66TH ST 90003
- Application / Permit
- 23016-20000-31596
- Plan Check / Job No.
- B23VN12542
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- **Eplan ** Conversion of existing Attached car garages under (E) duplex into a ADU per GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 1/1/2025
- Issuing Office
- Current Status
- Issued on 1/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | YASHAR EMAMI |
| Corrections Issued | 9/26/2023 | YASHAR EMAMI |
| Quality Review Completed | 10/5/2023 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 4/9/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/20/2024 | YASHAR EMAMI |
| Issued | 1/1/2025 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 2/5/2024 | MARIA VENDIVIL |
| Hydrant and Access approval | Cleared | 3/18/2024 | KURT CORRAL |
| Address approval | Cleared | 3/20/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 3/20/2024 | AMBER CAMPBELL |
| Construction near power lines | Cleared | 4/10/2024 | RIDWAN HARDY |
| Permit | Cleared | 5/23/2024 | AMBER CAMPBELL |
| DAS Clearance | Cleared | 7/11/2024 | REZA HAGHIGHAT |
| Green Code | Cleared | 9/20/2024 | REZA HAGHIGHAT |
| Tenant Habitability Plan | Cleared | 9/20/2024 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Banning,, George Kwame; Lic. No.: C53074 | 7550 LILY COURT FONTANA, CA 92336 |
| Engineer | Banning,, George Kwame; Lic. No.: NA53074 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/23/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Partial Approval | JOHN QUINTANILLA |
| Green Building Rough | 12/11/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2025 | Approved | ANTHONY RAMOS |
| Insulation | 12/24/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 1/13/2026 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 1/13/2026 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 1/13/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Drywall Nailing | 1/14/2026 | Not Ready for Inspection | BARRY HACHE |
| Drywall Nailing | 2/3/2026 | Approved | JOHN QUINTANILLA |
| Wood Frame | 2/3/2026 | Approved | JOHN QUINTANILLA |
| Final | 5/29/2026 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 5/29/2026 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 5/29/2026 | Approved | JOHN QUINTANILLA |