8039-8041 N MORSE AVE 91605
Certificate Information: 8039-8041 N MORSE AVE 91605
- Application / Permit
- 23016-20000-31441
- Plan Check / Job No.
- B23VN12487
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). COMPLY WITH DEPARTMENT ORDER effective date 05/09/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2023 | JESSE ARELLANO |
| Corrections Issued | 9/20/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 9/27/2023 | APPLICANT |
| Applicant returned to address corrections | 2/20/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 2/27/2024 | ANGELICA MARTINEZ |
| Issued | 2/29/2024 | APPLICANT |
| CofO in Progress | 3/11/2025 | VINCENT HANLEY |
| CofO Issued | 3/17/2025 | RUBEN SALAS |
| Permit Finaled | 3/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/13/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/26/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/8/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 3/26/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/29/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/2/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 6/3/2024 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/3/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 6/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/20/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/27/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 6/27/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/27/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 6/27/2024 | Approved | GREGG CUMMINGS |
| Insulation | 7/11/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 7/12/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/12/2024 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 7/22/2024 | Conditional Approval | SALVADOR MARTINEZ |
| Final | 11/14/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/14/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 11/14/2024 | Approved | GREGG CUMMINGS |
| Final | 1/27/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/27/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/10/2025 | Approved | VINCENT HANLEY |
| Final | 3/10/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/10/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/10/2025 | Approved | VINCENT HANLEY |