9656-9658 N HASKELL AVE 91343
Certificate Information: 9656-9658 N HASKELL AVE 91343
- Application / Permit
- 23016-20000-31355
- Plan Check / Job No.
- B23VN12466
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT EXISTING GARAGE AND BREEZEWAY TO NEW SINGLE FAMILY DWELLING PER SB9
- Permit Issued
- Issued on 10/27/2023
- Issuing Office
- Current Status
- CofO Issued on 1/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | SELLA BENYAMIN |
| Corrections Issued | 9/19/2023 | SELLA BENYAMIN |
| Quality Review Completed | 9/20/2023 | STEVEN KIM |
| Building Plans Picked Up | 9/20/2023 | APPLICANT |
| Plan Check Approved | 10/27/2023 | SELLA BENYAMIN |
| Issued | 10/27/2023 | APPLICANT |
| CofO in Progress | 11/25/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 1/7/2026 | RUBEN SALAS |
| CofO Issued | 1/7/2026 | RUBEN SALAS |
| Permit Finaled | 1/7/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | RYAN KIM |
| Sewer availability | Cleared | 9/25/2023 | RYAN KIM |
| Senate Bill 9 | Cleared | 10/16/2023 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/23/2024 | Partial Approval | RAUL OLAGI |
| Special/Order Compliance | 5/23/2024 | Corrections Issued | RAUL OLAGI |
| Deputy Drilled-In Anchors | 5/28/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/29/2024 | Partial Inspection | RAUL OLAGI |
| Special/Order Compliance | 5/29/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/12/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 7/12/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 7/12/2024 | Corrections Issued | RAUL OLAGI |
| MERV13>=Rough | 7/12/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 7/12/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 7/31/2024 | Approved | RAUL OLAGI |
| Insulation | 7/31/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/31/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 7/31/2024 | Approved | RAUL OLAGI |
| Final | 8/6/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/6/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| MERV13>=Final | 8/6/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 8/6/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Drywall Nailing | 8/19/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/19/2024 | Approved | RAUL OLAGI |
| Shower Pan | 8/19/2024 | Approved | RAUL OLAGI |
| Sewer | 9/12/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 9/12/2024 | Approved | RAUL OLAGI |
| Final | 1/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 1/29/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| MERV13>=Final | 1/29/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 1/29/2025 | Approved | SALVADOR MARTINEZ |
| Final | 11/25/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 11/25/2025 | Approved | GAREN HAYRAPETYAN |
| MERV13>=Final | 11/25/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 11/25/2025 | Approved | GAREN HAYRAPETYAN |