9511-9513 N REMICK AVE 91331
Certificate Information: 9511-9513 N REMICK AVE 91331
- Application / Permit
- 23016-20000-31343
- Plan Check / Job No.
- B23VN12459
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 10/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2023 | JESSE ARELLANO |
| Corrections Issued | 9/19/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 10/11/2023 | APPLICANT |
| Plan Check Approved | 10/17/2023 | SERGIO MUNIZ |
| Issued | 10/17/2023 | APPLICANT |
| CofO in Progress | 7/19/2024 | MICHEL ABAJAN |
| CofO Issued | 8/5/2024 | RUBEN SALAS |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/16/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/3/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 4/4/2024 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Approved | MICHEL ABAJAN |
| Sewer | 4/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/5/2024 | Partial Approval | MICHEL ABAJAN |
| Sewer | 4/5/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 4/16/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/26/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/26/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 4/26/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 4/26/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 4/26/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/26/2024 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/10/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/10/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/10/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/16/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 5/16/2024 | Partial Approval | JOHN COLEMAN |
| Shower Pan | 5/16/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 5/16/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Insulation | 5/21/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/21/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/24/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/24/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 7/1/2024 | Approved | MICHEL ABAJAN |
| Final | 7/1/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/1/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/1/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 7/1/2024 | Approved | MICHEL ABAJAN |
| Final | 7/12/2024 | OK to Issue CofO | MICHEL ABAJAN |